Skip to content
All companies
Reviewed company record

Amazon Web Services

Organization ID: CMP-0152

A site-linked view of this organization’s current published roles and data center portfolio.

Published sites
31
Programs
9
Markets
11
Infrastructure claims
57
Operating capacity
—

Infrastructure portfolio

Reviewed project-level claims associated with this company’s published site and program roles.

33 of 41 records covered
Power & interconnection
37
published claims
Generation & storage
2
published claims
Cooling & water
7
published claims
Fiber & connectivity
0
published claims
Site systems
11
published claims

These are claim counts, not additive capacity totals. A company role or project utility field does not identify a serving substation, transmission line, or interconnection point.

Project portfolio

Sites and programs remain separately identified throughout the portfolio.

Open filtered directory
Amazon–STACK Highway 3 Technology Park CampusSite
Louisiana
Construction—2 claims
Amazon–STACK Northwest Louisiana Campus ProgramProgram
Louisiana
Status under reviewNot rolled up3 claims
Amazon–STACK State Line Road CampusSite
Louisiana
Construction—0 claims
AWS Asia Pacific (New Zealand) RegionProgram
Status under reviewNot rolled up2 claims
AWS BDE / ZAZ082 Data Center CampusSite
Aragon
Construction—1 claim
AWS Boardman Exascale Development AreaSite
Oregon
Preconstruction—0 claims
AWS Canton Madison Mega Site CampusSite
Mississippi
Partially operational—1 claim
AWS CAR / ZAZ102 Data Center CampusSite
Aragon
Preconstruction—1 claim
AWS Clinton Delphi RetrofitSite
Mississippi
Operating—1 claim
AWS Dublin Data Center CampusSite
Ohio
Operating—1 claim
AWS El Burgo de Ebro Existing Data Center SiteSite
Aragon
Operating—0 claims
AWS Europe (Spain) / Aragon RegionProgram
Aragon
Status under reviewNot rolled up2 claims
AWS European Sovereign Cloud — Brandenburg RegionSite
Brandenburg
Operating—4 claims
AWS Falls Township Data Center CampusSite
Pennsylvania
Preconstruction—2 claims
AWS Hobart Data Center CampusSite
Indiana
Proposed—1 claim
AWS Huesca Existing Data Center SiteSite
Aragon
Operating—0 claims
AWS Mattameade Data Center CampusSite
Virginia
Preconstruction—2 claims
AWS Mississippi Madison-Hinds ProgramProgram
Mississippi
Partially operationalNot rolled up2 claims
AWS New Albany Data Center CampusSite
Ohio
Operating—2 claims
AWS Northern Indiana Expansion ProgramProgram
Indiana
Status under reviewNot rolled up3 claims
AWS PDX-154 Boardman Airport CampusSite
Oregon
Preconstruction—1 claim
AWS PDX-4 Boardman CampusSite
Oregon
Operating—1 claim
AWS Project Green Montgomery County CampusSite
Missouri
Preconstruction—3 claims
AWS Project Rainier — St. Joseph County SiteSite
Indiana
Partially operational—4 claims
AWS Ridgeland Costa Site CampusSite
Mississippi
Construction—0 claims
AWS Salem Township Nuclear CampusSite
Pennsylvania
Preconstruction1,920 MWContracted1 claim
AWS Saudi Arabia RegionProgram
Status under reviewNot rolled up0 claims
AWS South America (Chile) RegionProgram
Status under reviewNot rolled up2 claims
AWS Ulsan AI ZoneProgram
31
Status under reviewNot rolled up0 claims
AWS US West (Oregon) Eastern Oregon ProgramProgram
Oregon
Status under reviewNot rolled up2 claims
AWS VDG1 / ZAZ080 Data Center CampusSite
Aragon
Construction—1 claim
AWS VDG2 / ZAZ100 Data Center CampusSite
Aragon
Construction—1 claim
AWS Villanueva de Gallego Existing Data Center SiteSite
Aragon
Operating—0 claims
AWS Warren County Data Center CampusSite
Mississippi
Preconstruction—1 claim
AWS WQA / ZAZ081-111 Data Center CampusSite
Aragon
Construction—1 claim
AWS–Vistra Comanche Peak Power-Supply ProjectPower supply agreement
Texas
Preconstruction1,200 MWContracted2 claims
Birchwood AWSSite
Virginia
Delayed—1 claim
Cipher Black Pearl AI Data Center CampusSite
Texas
Partially operational300 MWContracted2 claims
GW RanchSite
Texas
Preconstruction—2 claims
Northeast Creek Technology CampusSite
Virginia
Preconstruction—1 claim
Wilderness CrossingSite
Virginia
Proposed—1 claim