AWS Northern Indiana Expansion Program

Northern Indiana, Indiana, United StatesStatus Under Review
Capacity
See sites
0 constituent sites
Lead participant
Amazon Data Services, Inc.
Developer
Last updated
Aug 25, 2026
Most recent public record update

About AWS Northern Indiana Expansion Program

Regional AWS program announced in November 2025 for new, still-undisclosed campuses; explicitly additional to New Carlisle. AWS Northern Indiana Expansion Program is in Northern Indiana, IN, US and is a program with announced status. Participants include Amazon Data Services, Inc. as developer, Amazon Web Services as operator, Northern Indiana Public Service Company LLC as utility. Published specifications include 2400 MW contracted supply, 1200 MW contracted supply, 3000 MW onsite generation nameplate. Development comprises Program announcement and site development (development), NIPSCO service ramp (approved). Key milestones include Retail service scheduled to begin. (2027-01-01) and Load scheduled to reach up to 2.4 GW. (2032-12-31). retail large load service — 2400 MW: 15-year special contract begins 2027 and ramps through end-2032; utility-service capacity, not IT load. dedicated generation portfolio — 3000 MW nameplate: Two CCGT facilities and one four-hour battery; excess over 2.4-GW load addresses accreditation/reserve requirements. Permitting includes large load special contract and ppa for Amazon Special Contract / Cause 46322 (approved).

Projects sharing a market, utility, or organization.

2 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Contracted Supply2,400 MWFact · AWS Northern Indiana Expansion Program
Contracted Supply1,200 MWFact · AWS Northern Indiana Expansion Program
Onsite Generation3,000 MWFact · AWS Northern Indiana Expansion Program

Development

2 phases · 5 milestones
Program announcement and site developmentAnnounced Or Preconstruction

No campus/building count is created until public site evidence resolves the physical portfolio.

NIPSCO service rampAnnounced Or Preconstruction

Contracted utility-service ramp; not a physical construction phase.

Sep 18, 2025
Amazon–NIPSCO customer contract executed
Completed
Nov 24, 2025
AWS announces additional Northern Indiana campuses
Completed
Jun 17, 2026
IURC approves special contract and PPA
Completed
Jan 1, 2027
Retail service scheduled to begin
Forecast
Dec 31, 2032
Load scheduled to reach up to 2.4 GW
Forecast

Infrastructure

Utility ServiceSecured Or Contracted

2,400 MW

15-year special contract begins 2027 and ramps through end-2032; utility-service capacity, not IT load.

Electric GridSecured Or Contracted

3,000 MW nameplate

Two CCGT facilities and one four-hour battery; excess over 2.4-GW load addresses accreditation/reserve requirements.

Electric GridSecured Or Contracted

NIPSCO builds/owns required transmission, with project costs allocated through the approved structure.

Constituent-site map

0 of 0 constituent sites mapped
Child-site facts
0
Mapped child sites
0
Capacity figures
0

No map point available

Facts & sources

Published claims and their source links.

9 facts
Announced Investment
$15,000 millions
Fact
Planned Data Center Capacity
2,400 MW
Fact
Service Start Target
2027-01-01
Fact
Full Ramp Target
2032-12-31
Fact
Direct Jobs Expected
1,100 jobs
Fact
Customer Savings Projection
$1,000 millions
Fact
Load Reduction Option
1,200 MW
Fact
Dedicated Generation Portfolio Nameplate
3,000 MW
Fact
Energy Infrastructure Investment Estimate
$7,000 millions
Fact