AWS Ulsan AI Zone
Ulsan, South Korea · 31Status under reviewProgram
- Headline capacity
- See constituent sites
- Updated
- Oct 28, 2026
Construction began August 29, 2025. The first 41 MW is targeted for November 2027 and the 103 MW facility for February 2029. A future 1 GW expansion remains a vision rather than an approved phase.
Program relationships
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Initial AWS AI Zone servicePlanned
Service availability depends on physical campus delivery.
Milestones (1)
AWS AI Zone expected to operate from Ulsan
2027 · Forecast / planned record
Forecast · Event type not stated
Source not linkedParticipants
Amazon Web Services
Operator
Sources by role
Operator (1)
- SK Group and AWS team up to build cloud infrastructure · Jun 22, 2025 · Primary
Other participants (1)
SK hynix
Supplier
Sources by role
Supplier (1)
- SK Group and AWS team up to build cloud infrastructure · Jun 22, 2025 · Primary
Additional project facts
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (1)
SK–AWS Ulsan AI Data Center
Under construction · Ulsan, South Korea
Same locality: Ulsan