Skip to content
All records
Data center siteSite record

AWS Canton Madison Mega Site Campus

Canton / Madison County Mega Site, Mississippi, United StatesPartially operational
Capacity
No public figure
Lead participant
Amazon Data Services, Inc.
Developer
Last updated
Aug 25, 2026
Most recent public record update

About AWS Canton Madison Mega Site Campus

AWS's Canton campus has five operating buildings and continued buildout at the Madison Mega Site. AWS Canton Madison Mega Site Campus is located in Canton / Madison County Mega Site, MS, US and is a data center campus in partially operational status. Participants include Amazon Web Services, Inc. as operator, Amazon Data Services, Inc. as developer. Development comprises Initial operating tranche (operating), Continued Canton buildout (construction). Key milestones include JAN100 phases II and III receive construction-stormwater coverage (2026-05-13) and Amazon confirms five operating Canton buildings (2026-06-09). recycled wastewater cooling: Amazon targets use of treated wastewater for Canton cooling by 2027. Permitting includes synthetic minor operating air permit for Amazon Data Services Madison Mega Site (issued) and construction stormwater coverage for Amazon Data Services MCEDA JAN100 phases II and III (issued).

Program relationships

1 linked

Projects sharing a market, utility, or organization.

3 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

2 phases · 3 milestones
Initial operating trancheOperational

Five operating buildings verified June 2026; MW undisclosed.

5 buildings

Continued Canton buildoutUnder Construction

At least five additional buildings implied by Amazon spokesperson, but no exact final count or phase dates published.

Jan 13, 2026
MDEQ board issues Canton synthetic-minor operating permit
Completed
May 13, 2026
JAN100 phases II and III receive construction-stormwater coverage
Completed
Jun 9, 2026
Amazon confirms five operating Canton buildings
Completed

Infrastructure

Cooling SystemPlanned Or Represented

Amazon targets use of treated wastewater for Canton cooling by 2027.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
0

No map point available

Cooling & water: 1

Facts & sources

Published claims and their source links.

14 facts
Current Status
Partially operational
Actual
Operating Building Count
5
Reported Rounded
Future Buildout At Least Doubles
True
Actual
Site Area Reported
927 acres
Reported Rounded
Site Name
Madison County Mega Site
Actual
Permit Code
JAN100
Actual
Synthetic Minor Operating Permit
True
Actual
Construction Stormwater Phases
II and III
Actual
Recycled Wastewater Cooling Planned
True
Actual
Recycled Wastewater Target Year
2027
Reported Rounded
Campus It Capacity Disclosed
False
Actual
Site Investment Disclosed
False
Actual
Permit Applicant
Amazon Data Services
Actual
Program Parent
AWS Mississippi Madison-Hinds Program
Actual