Data center siteSite record

Crusoe–Microsoft Abilene

Abilene, Texas, United StatesPreconstruction
Capacity
900 MW
Planned / design
Lead participant
Crusoe
Developer
Last updated
Aug 18, 2026
Most recent public record update

About Crusoe–Microsoft Abilene

Crusoe announced a separate 900 MW, two-building Abilene campus for Microsoft in March 2026. The first building is forecast to energize in mid-2027; the design includes 900 MW of on-site generation, battery storage and two 336 MW IT-load buildings.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design900 MWDesign · Crusoe–Microsoft Abilene

Development

1 phases · 0 milestones
Microsoft campus initial scopeAnnounced Or Preconstruction

Separate 900 MW campus announced in March 2026.

2 buildings

Infrastructure

Onsite Natural Gas GenerationPlanned Or Represented

900 MW generation

Dedicated power plant and BESS support the new Microsoft campus; not an additional data center project.

Battery StoragePlanned Or Represented

Dedicated power plant and BESS support the new Microsoft campus; not an additional data center project.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Generation & storage: 2

Facts & sources

Published claims and their source links.

1 facts
Planned Power Capacity
900 MW
Design