Scope and capacity

Crusoe announced a separate 900 MW, two-building Abilene campus for Microsoft in March 2026. The first building is forecast to energize in mid-2027; the design includes 900 MW of on-site generation, battery storage and two 336 MW IT-load buildings.

Headline: 900 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Planned power capacity · 900 MW

Planned / design or future potential · Crusoe–Microsoft Abilene (Project)

Claim 317 · Recorded claim type: Design · Review: Approved · Claim date: Mar 27, 2026

Headline treatment: Selected headline

  1. Crusoe announces new 900 MW Microsoft AI campus in Abilene

    Crusoe · Document date: Mar 27, 2026 · Primary

    Source reference: SRC-0017 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure

Counterparties and capital

Crusoe · Developer · CMP-0005

Microsoft · Customer, Tenant · CMP-0017