IREN Childress Horizon AI Data Center Campus

Childress, Texas, United StatesUnder construction
Capacity
200 MW
Contracted
Lead participant
IREN
Operator
Last updated
Aug 27, 2026
Most recent public record update

About IREN Childress Horizon AI Data Center Campus

IREN is delivering four Horizon data centers at its Childress campus under a multi-year Microsoft agreement. Horizon 1–4 collectively provide 200 MW of contracted critical IT load within the broader 750 MW campus. IREN, Microsoft is associated with the development in Childress, Childress County, TX, US. The disclosed development scope includes 200 MW contracted critical IT across Horizon 1–4; 750 MW broader campus; phased deployment through 2026. Power and physical infrastructure include liquid-cooled GPU data centers within IREN’s Childress power campus. IREN states Horizon 1–4 will collectively provide 200 MW of critical IT load under the Microsoft agreement.

Projects sharing a market, utility, or organization.

4 related

Capacity

Contracted
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Contracted Supply200 MWActual · IREN Childress Horizon AI Data Center Campus
Contracted Supply200 MWActual · IREN Childress Horizon AI Data Center Campus

Development

1 phases · 2 milestones
Construction programUnder Construction

Project-wide phase for IREN Childress Horizon AI Data Center Campus; capacity class is contracted supply.

Nov 3, 2025
IREN Horizon 1–4 Childress development disclosed
Completed
Four-phase Microsoft deployment under construction and commissioning
Forecast

Infrastructure

Electric GridPlanned Or Represented

200 MW

IREN states Horizon 1–4 will collectively provide 200 MW of critical IT load under the Microsoft agreement.

Site FacilityPlanned Or Represented

Liquid-cooled GPU data centers within IREN’s Childress power campus.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
IREN Childress campus | Childress | Texas
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
200 MW
Actual
Capacity Basis
IREN states Horizon 1–4 will collectively provide 200 MW of critical IT load under the Microsoft agreement.
Actual
Location Context
IREN Childress campus | Childress | Texas
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
200 MW
Actual
Capacity Basis
IREN states Horizon 1–4 will collectively provide 200 MW of critical IT load under the Microsoft agreement.
Actual
Development Scale
200 MW contracted critical IT across Horizon 1–4
Actual
Development Milestone
750 MW broader campus
Actual
Power Arrangement
Phased deployment through 2026.
Actual
Site Configuration
IREN Childress campus | Childress | Texas
Actual