Skip to content

Vantage VA1 Ashburn Data Center Campus

Sterling, Virginia, United StatesPartially operational
Evidence
Planned critical IT
206 MW
Updated
Oct 28, 2026

Vantage's first Ashburn campus combines operating facilities with continued full-build development. The current campus plan totals 206 MW of IT capacity across six data centers. Vantage Data Centers is publicly identified in the project record for Sterling, Loudoun County, VA, US. The disclosed development record includes 52-acre campus; six data centers at full build; 206 MW planned IT capacity; approximately 1.7 million square feet. Power and infrastructure include dense multi-building Ashburn campus with flexible data modules and extensive carrier access. Vantage states VA1 will provide 206 MW of IT capacity at full build.

Capacity

Reported capacity

Design

206 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating and expansion programPartially operational

Project-wide phase for Vantage VA1 Ashburn Data Center Campus; capacity remains classified as it load.

Milestones (2)
Vantage Ashburn I project status and capacity disclosed

Aug 27, 2026 · Recorded actual event

Completed · Announced

Source not linked
Operational multi-building campus with continuing full-build development

Date not disclosed · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Vantage Data Centers

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

45200 Vantage Data Plaza | Sterling | Loudoun County | Virginia

Source

Development scale

Actual

52-Acre campus

Source

Development milestone

Actual

Six data centers at full build

Source

Site configuration

Actual

Approximately 1.7 million square feet.

Source

Technical specifications

Power arrangement

Actual

206 MW planned IT capacity

Source

Additional project facts

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

Vantage states VA1 will provide 206 MW of IT capacity at full build.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Partially operational

206 MW

Vantage states VA1 will provide 206 MW of IT capacity at full build.

Site facility

Partially operational

Dense multi-building Ashburn campus with flexible data modules and extensive carrier access.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (4)
CyrusOne NVA1–NVA3 Sterling Data Center Campus

Partially operational · Sterling, Virginia, United States

Same locality: Sterling

Compare in a collection
CyrusOne NVA4 Sterling Data Center

Partially operational · Sterling, Virginia, United States

Same locality: Sterling

Compare in a collection
CyrusOne NVA5–NVA7 Sterling Data Center Campus

Partially operational · Sterling, Virginia, United States

Same locality: Sterling

Compare in a collection
CyrusOne NVA8 Sterling Data Center

Partially operational · Sterling, Virginia, United States

Same locality: Sterling

Compare in a collection