ODATA Mexico Hyperscale Network
- Headline capacity
- See constituent sites
- Updated
- Oct 28, 2026
All four campuses have operating capacity. QR01 is marketed at 32 MW, QR02 at 30 MW, QR03 has its first 72 MW building operating within a 300 MW five-building buildout, and QR04 has 12 MW operating within a 24 MW design.
Constituent sites / phases
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Milestones (1)
Feb 27, 2025 · Recorded actual event
Completed · Event type not stated
Source not linkedParticipants
Developer · Operator
Sources by role
Developer / Operator (1)
Developer (1)
- ODATA company history · Corroborating
Other participants (1)
Supplier
Sources by role
Supplier (1)
- ODATA announces energization of Mexico's largest data center campus · Feb 27, 2025 · Primary
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (6)
Operational
200 MW
First stage of regional utility infrastructure energized.
Planned or represented
400 MW
Target utility capacity through 400 kV switching station, transmission and substations.
Operational
400 kV
400 kV switching-station expansion included in energization works.
Operational
6.2 miles
New high-voltage transmission segment supporting regional delivery.
Operational
2 substations
Two substations included in regional works.
Operational
4 campuses
Underground fiber routes link QR01 through QR04.
Constituent-site map
Public-source research. Plans may change. See Evidence for sources and qualifications.