Cartis diligence evidence schedule
ODATA Mexico Hyperscale Network
PRJ-0274 · Program · Querétaro–Guanajuato corridor, Mexico
Record last updated Oct 28, 2026
Scope and capacity
All four campuses have operating capacity. QR01 is marketed at 32 MW, QR02 at 30 MW, QR03 has its first 72 MW building operating within a 300 MW five-building buildout, and QR04 has 12 MW operating within a 24 MW design.
Headline: See constituent sites
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (7)
Member campus count · 4 campuses
Actual · ODATA Mexico Hyperscale Network (Project)
Claim 26116 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- ODATA announces energization of Mexico's largest data center campus
ODATA · Document date: Feb 27, 2025 · Corroborating
Source reference: SRC-1474 · Company announcement · Recorded authority: Party primary
Source URL
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
- Scalable and adaptive data centers in Mexico
Aligned Data Centers · Document date: Not stated · Primary
Source reference: SRC-1469 · Company announcement · Recorded authority: Party primary
Source URL
https://aligneddc.com/mexico-data-centers/
https://aligneddc.com/mexico-data-centers/
- ODATA company history
ODATA · Document date: Not stated · Corroborating
Source reference: SRC-1481 · Company announcement · Recorded authority: Party primary
Source URL
https://odatacolocation.com/en/sobre-nos/
https://odatacolocation.com/en/sobre-nos/
Energized utility capacity · 200 MW
Actual · ODATA Mexico Hyperscale Network (Project)
Claim 26117 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- ODATA announces energization of Mexico's largest data center campus
ODATA · Document date: Feb 27, 2025 · Primary
Source reference: SRC-1474 · Company announcement · Recorded authority: Party primary
Source URL
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
Target utility capacity · 400 MW
Planned / design or future potential · ODATA Mexico Hyperscale Network (Project)
Claim 26118 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- ODATA announces energization of Mexico's largest data center campus
ODATA · Document date: Feb 27, 2025 · Primary
Source reference: SRC-1474 · Company announcement · Recorded authority: Party primary
Source URL
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
- Scalable and adaptive data centers in Mexico
Aligned Data Centers · Document date: Not stated · Corroborating
Source reference: SRC-1469 · Company announcement · Recorded authority: Party primary
Source URL
https://aligneddc.com/mexico-data-centers/
https://aligneddc.com/mexico-data-centers/
Transmission voltage · 400 kV
Actual · ODATA Mexico Hyperscale Network (Project)
Claim 26119 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- ODATA announces energization of Mexico's largest data center campus
ODATA · Document date: Feb 27, 2025 · Primary
Source reference: SRC-1474 · Company announcement · Recorded authority: Party primary
Source URL
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
New transmission length · 6.2 miles
Actual · ODATA Mexico Hyperscale Network (Project)
Claim 26120 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- ODATA announces energization of Mexico's largest data center campus
ODATA · Document date: Feb 27, 2025 · Primary
Source reference: SRC-1474 · Company announcement · Recorded authority: Party primary
Source URL
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
New substation count · 2 substations
Actual · ODATA Mexico Hyperscale Network (Project)
Claim 26121 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- ODATA announces energization of Mexico's largest data center campus
ODATA · Document date: Feb 27, 2025 · Primary
Source reference: SRC-1474 · Company announcement · Recorded authority: Party primary
Source URL
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
Campuses linked by underground fiber · True
Source report · ODATA Mexico Hyperscale Network (Project)
Claim 26122 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- ODATA announces energization of Mexico's largest data center campus
ODATA · Document date: Feb 27, 2025 · Primary
Source reference: SRC-1474 · Company announcement · Recorded authority: Party primary
Source URL
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
https://odatacolocation.com/en/blog/imprensa/odata-announces-energization-of-mexicos-largest-data-center-campus-solving-energy-scarcity-for-the-development-of-data-centers-in-queretaro/
Counterparties and capital
Aligned Data Centers · Owner · CMP-0165
Ammper · Supplier · CMP-0740
ODATA · Developer, Operator · CMP-0164
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.