AirTrunk JHB1 Data Center Campus

Johor Bahru, Johor, MalaysiaPartially operational
Capacity
50 MW
Operating critical IT
Lead participant
AirTrunk
Developer
Last updated
Aug 25, 2026
Most recent public record update

About AirTrunk JHB1 Data Center Campus

First AirTrunk Malaysia campus; initial phases are live while the remaining buildout continues. AirTrunk JHB1 Data Center Campus is in Johor Bahru, Johor, MY and is a data center campus with partially operational status. Participants include AirTrunk as developer, Tenaga Nasional Berhad as utility. Published specifications include 50 MW operating it capacity, 150 MW future potential, 100 MW planned capacity. Development comprises Initial JHB1 phases (operational), Remaining 100-MW expansion (under construction). Key milestones include Remaining 100-MW expansion announced underway. (2024-08-09) and Rooftop solar development announced. (2024-11-20). grid connection: TNB grid connection; service amount not separately disclosed. rooftop solar — 1 MW: Proposed rooftop solar development. Permitting includes campus development and utility approvals for JHB1 (partially verified).

Program relationships

1 linked

Projects sharing a market, utility, or organization.

4 related

Capacity

Operating critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load50 MWFact · AirTrunk JHB1 Data Center Campus
Future Potential150 MWFact · AirTrunk JHB1 Data Center Campus
Onsite Generation1 MWFact · AirTrunk JHB1 Data Center Campus

Development

2 phases · 4 milestones
Initial JHB1 phasesOperational

More than 50 MW opened in July 2024.

Remaining 100-MW expansionUnder Construction

The initial tranche had a mid-2025 delivery target; completion of the full 100-MW expansion has not been publicly announced.

Jan 19, 2023
JHB1 announced
Completed
Jul 30, 2024
Initial JHB1 phases opened
Completed
Aug 9, 2024
Remaining 100-MW expansion announced underway
Completed
Nov 20, 2024
Rooftop solar development announced
Completed

Infrastructure

Electric GridPartially Operational

TNB grid connection; service amount not separately disclosed.

Renewable Energy SupplyPlanned Or Represented

1 MW

Proposed rooftop solar development.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 2

Facts & sources

Published claims and their source links.

9 facts
Site Area
10.3 hectares
Actual
Initial Operational Capacity
50 MW
Fact
Campus Capacity Potential
150 MW
Fact
Remaining Expansion
100 MW
Fact
Design Pue
1.15
Fact
Design Energy Reduction
23 percent
Fact
Announced Investment
1,000 AUD millions
Fact
Commercial Status
Fully contracted
Fact
Rooftop Solar Capacity
1 MW
Fact