STACK JHB01 Iskandar Puteri Data Center Campus

Iskandar Puteri, Johor, MalaysiaUnder construction
Evidence
Planned critical IT
220 MW
Updated
Oct 28, 2026
Utility
Tenaga Nasional Berhad

STACK JHB01 Iskandar Puteri Data Center Campus, also known as STACK Johor Bahru Campus, is a data center project in Iskandar Puteri, Johor, MY developed and operated by STACK Infrastructure. 10.8-hectare flagship Johor Bahru campus with two facilities totaling about one million square feet and 220 MW. TNB 275 kV infrastructure, onsite substation, redundant site entries and a fiber ring to multiple telecommunications networks. The January 2025 project announcement states 220 MW, while STACK’s current APAC index reports 216 MW for Johor Bahru. The cited identity or capacity sources conflict and do not establish a single project-scoped capacity figure.

Capacity

Reported capacity

Design

220 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development, permitting and phased deliveryUnder construction

The January 2025 project announcement states 220 MW, while STACK’s current APAC index reports 216 MW for Johor Bahru. The available public sources do not establish a single project-scoped capacity figure.

Milestones (2)
STACK announced Johor Bahru campus

Jan 14, 2025 · Recorded actual event

Completed · Announced

Source not linked
Initial delivery target stated as Q4 2026

2026 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

STACK Infrastructure

Developer

Sources by role
Developer (1)
Other participants (1)
Tenaga Nasional Berhad

Utility provider

Sources by role
Utility provider (1)

Site & development

Location context

Actual

STACK Johor Bahru Campus | Iskandar Puteri | Johor | MY

Source

Location context

Actual

STACK Johor Bahru Campus | Iskandar Puteri | Johor | MY

Source

Site area

Design

10.8 hectares

Source

Building count

Design

2 facilities

Source

Building area

Design

1,000,000 square feet

Source

Additional project facts

Lifecycle status

Actual

Construction

Source

Capacity basis

Actual

STACK Infrastructure publishes 220 MW of critical IT capacity for this record boundary.

Source

Lifecycle status

Actual

Construction

Source

Initial delivery target

Forecast

Q4 2026

Source

Infrastructure & permits

Technical details (3)
Electric grid

Planned or represented

TNB 275 kV infrastructure, onsite substation, redundant site entries and a fiber ring to multiple telecommunications networks.

Fiber

Planned or represented

STACK markets diverse fiber and carrier-neutral deployment options; installed and contracted capacity remain distinct.

Electric grid

Planned or represented

275 kV

TNB high-voltage infrastructure and an onsite substation support the phased campus plan.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (4)
AirTrunk JHB1 Data Center Campus

Partially operational · Johor Bahru, Johor, Malaysia

Shared participant: Tenaga Nasional Berhad · Same market: Johor, Malaysia

Compare in a collection
AirTrunk JHB2 Data Center Campus

Under construction · Johor Bahru, Johor, Malaysia

Shared participant: Tenaga Nasional Berhad · Same market: Johor, Malaysia

Compare in a collection
AirTrunk JHB3 Data Center Campus

Status under review · Johor Bahru, Johor, Malaysia

Shared participant: Tenaga Nasional Berhad · Same market: Johor, Malaysia

Compare in a collection
AirTrunk JHB4 Data Center Campus

Status under review · Johor Bahru, Johor, Malaysia

Shared participant: Tenaga Nasional Berhad · Same market: Johor, Malaysia

Compare in a collection