AirTrunk Malaysia Data Center Platform

Johor Bahru, Johor, MalaysiaStatus under reviewProgram
Evidence
Headline capacity
See constituent sites
Updated
Oct 28, 2026
Utility
ib vogt

AirTrunk's four-campus Malaysia platform; program-level power and aggregate capacity remain on the parent. AirTrunk Malaysia Data Center Platform is in Johor Bahru, Johor, MY and is a program with partially operational status.

Constituent sites / phases

Capacity

Platform capacity potential

Planned / design or future potential

700 MW

Source

Vppa solar capacity

Source report

30 MW

Generation capacity; not IT capacity

Source

Planned and operating platform IT load over

Planned / design or future potential

700 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

JHB3-JHB4 paired-campus expansionAnnounced or preconstruction

2 buildings

Combined MYR 12 billion / USD 3 billion investment and 280+ MW IT load.

Milestones (4)
Blackstone and CPP Investments agreed to acquire AirTrunk

Sep 4, 2024 · Recorded actual event

Completed · Event type not stated

Source not linked
AirTrunk announced JHB3 and JHB4

Apr 30, 2026 · Recorded actual event

Completed · Announced

Source not linked
Malaysia VPPA solar project commenced commercial operation

Jul 1, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
29.99 MWac solar project began commercial operations

Jul 1, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked

Participants

AirTrunk

Developer

Sources by role
Developer (1)
Developer (1)
Blackstone

Investor · Owner

Sources by role
Investor (1)
Investor (1)
Owner (1)
Owner (1)
CPP Investments

Investor · Owner

Sources by role
Investor (1)
Owner (1)
Owner (1)
Other participants (2)
Government of Malaysia

Government authority

Sources by role
Government authority (1)
ib vogt

Utility provider

Sources by role

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Combined platform investment

Source report

$6,800 millions

Source

Jhb3 jhb4 combined investment

Source report

$3,000 millions

Source

Platform acquisition value

Source report

24,000 AUD millions

Source

Total committed malaysia investment approximately

Actual

27 MYR billion

Source

Total committed malaysia investment USD approximately

Actual

$6.80 billion

Source

Jhb3 jhb4 investment

Actual

12 MYR billion

Source

Jhb3 jhb4 investment USD approximately

Actual

$3 billion

Source

Financing records

Paired campus development investment

MYR 12,000,000,000

Apr 30, 2026

Combined JHB3-JHB4 investment, approximately USD 3 billion; no campus allocation or financing instrument/lender list disclosed.

Parties & sources

AirTrunk (Developer and investment sponsor)

Site & development

Jhb3 jhb4 construction jobs over

Actual

3,000 jobs

Source

Additional project facts

Campus count

Actual

4 campuses

Source

Malaysia platform campus count

Actual

4 campuses

Source

Infrastructure & permits

Technical details (2)
Renewable energy supply

Operational

29.99 MWac

29.99-MWac solar project supporting Malaysia operations.

Renewable energy supply

Operational

29.99 MWac

Malaysia-wide operations support; no allocation to JHB3 or JHB4.

Public-source research. Plans may change. See Evidence for sources and qualifications.