Cartis diligence evidence schedule
AirTrunk JHB1 Data Center Campus
PRJ-0240 · Site · Johor Bahru, Johor, Malaysia
Record last updated Oct 28, 2026
Scope and capacity
First AirTrunk Malaysia campus; initial phases are live while the remaining buildout continues. AirTrunk JHB1 Data Center Campus is in Johor Bahru, Johor, MY and is a data center campus with partially operational status.
Headline: 150 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (9)
Site area · 10.3 hectares
Actual · AirTrunk JHB1 Data Center Campus (Project)
Claim 22498 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- IFC project disclosure: AirTrunk Johor
International Finance Corporation · Document date: Jul 14, 2026 · Corroborating
Source reference: SRC-1295
Source URL
https://disclosures.ifc.org/project-detail/SII/52336/airtrunk-johor
https://disclosures.ifc.org/project-detail/SII/52336/airtrunk-johor
- AirTrunk doubles down in Malaysia with JHB3 and JHB4
AirTrunk · Document date: Apr 30, 2026 · Corroborating
Source reference: SRC-1296
Source URL
https://airtrunk.com/airtrunk-doubles-down-in-malaysia-with-two-new-hyperscale-campuses-in-johor-bahru/
https://airtrunk.com/airtrunk-doubles-down-in-malaysia-with-two-new-hyperscale-campuses-in-johor-bahru/
- AirTrunk and Pekat Solar to develop rooftop solar at JHB1
AirTrunk · Document date: Nov 20, 2024 · Corroborating
Source reference: SRC-1291
Source URL
https://airtrunk.com/airtrunk-and-pekat-solar-to-develop-rooftop-solar-at-airtrunks-johor-bahru-data-centre-jhb1/
https://airtrunk.com/airtrunk-and-pekat-solar-to-develop-rooftop-solar-at-airtrunks-johor-bahru-data-centre-jhb1/
- AirTrunk JHB1 100MW expansion underway
AirTrunk · Document date: Aug 9, 2024 · Corroborating
Source reference: SRC-1290
Source URL
https://airtrunk.com/airtrunk-jhb1100mw-expansion-underway/
https://airtrunk.com/airtrunk-jhb1100mw-expansion-underway/
- AirTrunk opens AI-ready data centre in Malaysia
AirTrunk · Document date: Jul 30, 2024 · Primary
Source reference: SRC-1289
Source URL
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
- AirTrunk enters Malaysia with new 150MW hyperscale data centre
AirTrunk · Document date: Jan 19, 2023 · Corroborating
Source reference: SRC-1288
Source URL
https://airtrunk.com/airtrunk-enters-malaysia-with-new-150mw-hyperscale-data-centre-in-johor-bahru/
https://airtrunk.com/airtrunk-enters-malaysia-with-new-150mw-hyperscale-data-centre-in-johor-bahru/
- AirTrunk Malaysia locations
AirTrunk · Document date: Not stated · Corroborating
Source reference: SRC-1297 · Company announcement
Source URL
https://airtrunk.com/location/malaysia/
https://airtrunk.com/location/malaysia/
Initial operational capacity · 50 MW
Source report · AirTrunk JHB1 Data Center Campus (Project)
Claim 22499 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
Headline treatment: Not included in reviewed operating IT capacity
- AirTrunk opens AI-ready data centre in Malaysia
AirTrunk · Document date: Jul 30, 2024 · Primary
Source reference: SRC-1289
Source URL
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
Campus capacity potential · 150 MW
Planned / design or future potential · AirTrunk JHB1 Data Center Campus (Project)
Claim 22500 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- AirTrunk opens AI-ready data centre in Malaysia
AirTrunk · Document date: Jul 30, 2024 · Corroborating
Source reference: SRC-1289
Source URL
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
- AirTrunk enters Malaysia with new 150MW hyperscale data centre
AirTrunk · Document date: Jan 19, 2023 · Primary
Source reference: SRC-1288
Source URL
https://airtrunk.com/airtrunk-enters-malaysia-with-new-150mw-hyperscale-data-centre-in-johor-bahru/
https://airtrunk.com/airtrunk-enters-malaysia-with-new-150mw-hyperscale-data-centre-in-johor-bahru/
Remaining expansion · 100 MW
Source report · AirTrunk JHB1 Data Center Campus (Project)
Claim 22501 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- AirTrunk JHB1 100MW expansion underway
AirTrunk · Document date: Aug 9, 2024 · Primary
Source reference: SRC-1290
Source URL
https://airtrunk.com/airtrunk-jhb1100mw-expansion-underway/
https://airtrunk.com/airtrunk-jhb1100mw-expansion-underway/
Design PUE · 1.15
Source report · AirTrunk JHB1 Data Center Campus (Project)
Claim 22502 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- AirTrunk opens AI-ready data centre in Malaysia
AirTrunk · Document date: Jul 30, 2024 · Primary
Source reference: SRC-1289
Source URL
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
Design energy reduction · 23 percent
Source report · AirTrunk JHB1 Data Center Campus (Project)
Claim 22503 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- AirTrunk opens AI-ready data centre in Malaysia
AirTrunk · Document date: Jul 30, 2024 · Primary
Source reference: SRC-1289
Source URL
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
https://airtrunk.com/airtrunk-opens-ai-ready-data-centre-in-malaysia-accelerating-innovation-and-the-energy-transition/
Announced investment · 1,000 AUD millions
Source report · AirTrunk JHB1 Data Center Campus (Project)
Claim 22504 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- AirTrunk JHB1 100MW expansion underway
AirTrunk · Document date: Aug 9, 2024 · Primary
Source reference: SRC-1290
Source URL
https://airtrunk.com/airtrunk-jhb1100mw-expansion-underway/
https://airtrunk.com/airtrunk-jhb1100mw-expansion-underway/
Commercial status · Fully contracted
Source report · AirTrunk JHB1 Data Center Campus (Project)
Claim 22505 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- IFC project disclosure: AirTrunk Johor
International Finance Corporation · Document date: Jul 14, 2026 · Primary
Source reference: SRC-1295
Source URL
https://disclosures.ifc.org/project-detail/SII/52336/airtrunk-johor
https://disclosures.ifc.org/project-detail/SII/52336/airtrunk-johor
Rooftop solar capacity · 1 MW
Source report · AirTrunk JHB1 Data Center Campus (Project)
Claim 22506 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
Headline treatment: Generation capacity; not IT capacity
- AirTrunk and Pekat Solar to develop rooftop solar at JHB1
AirTrunk · Document date: Nov 20, 2024 · Primary
Source reference: SRC-1291
Source URL
https://airtrunk.com/airtrunk-and-pekat-solar-to-develop-rooftop-solar-at-airtrunks-johor-bahru-data-centre-jhb1/
https://airtrunk.com/airtrunk-and-pekat-solar-to-develop-rooftop-solar-at-airtrunks-johor-bahru-data-centre-jhb1/
Counterparties and capital
AirTrunk · Developer · CMP-0656
Tenaga Nasional Berhad · Utility provider · CMP-0658
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.