RecordStatusCapacityOwner / developerLast verified
AirTrunk MEL2 Melbourne Data Center CampusReviewed site record
Melbourne, Victoria, Australia
AirTrunk
Preconstruction
354 MW
Planned / designAirTrunk
Aug 27, 2026
STACK MEL02 Truganina Data Center CampusReviewed site record
Truganina, Victoria, Australia
STACK Infrastructure
Preconstruction
252 MW
Planned critical ITSTACK Infrastructure
Aug 28, 2026
AirTrunk MEL1 Melbourne Data Center CampusReviewed site record
Melbourne, Victoria, Australia
AirTrunk
Partially operational
185 MW
Planned critical ITAirTrunk
Aug 27, 2026
STACK MEL01 Melbourne Data Center CampusReviewed site record
Melbourne, Victoria, Australia
PowercorSTACK Infrastructure
Partially operational
180 MW
Planned / designSTACK Infrastructure
Aug 28, 2026
NEXTDC M4 Fishermans Bend Technology CampusReviewed site record
127 Todd Road, Port Melbourne, Victoria, Australia
NEXTDC LimitedVictorian Government
Entitled / Permitted
162 MW
Planned / designNEXTDC Limited
Aug 22, 2026
Vantage MEL1 Melbourne Data Center CampusReviewed site record
Tullamarine, Melbourne, Victoria, Australia
JemenaPrime Electrical & Data
Under construction
64 MW
Planned critical ITVantage Data Centers
Aug 28, 2026
Crusoe Port of Victoria CampusReviewed site record
Victoria, Texas, United States
Crusoe
Proposed
—
Not disclosedCrusoe
Aug 28, 2026
Every figure carries its capacity stage. Operating, contracted, planned/design and utility-service values remain distinct; generation is never used as site capacity, and unsupported values remain undisclosed.