NEXTDC's M4 campus at Fishermans Bend has development approval and remains in planning. The current operator page targets 150 MW of IT capacity and 26,400 square metres of technical space.
Capacity
Target IT capacity
Planned / design or future potential150 MW
Conflicting public evidence
Conflicting source claims
SourceBroader campus capacity
Planned / design or future potential162 MW
Conflicting public evidence
Conflicting source claims
SourceRack density design
Planned / design or future potential>1000 kW per rack
Power density; not a whole-site capacity
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Three-component campus concept announced in June 2025.
Current authoritative status; construction not evidenced.
No phase MW, start date or commissioning schedule disclosed.
Milestones (2)
Jun 12, 2025 · Recorded actual event
Completed · Announced
Source not linkedJan 19, 2026 · Recorded actual event
Completed · Permit approved
Source not linkedParticipants
Operator
Sources by role
Operator (1)
- M4 Technology Campus approved · Jan 19, 2026 · Corroborating
Operator (1)
- NEXTDC announces $2 billion AI Factory and Technology Campus at Fishermans Bend · Jun 12, 2025 · Primary
Operator (1)
- M4 Melbourne Data Centre · Corroborating
Other participants (1)
Government authority
Sources by role
Government authority (1)
- M4 Technology Campus approved · Jan 19, 2026 · Corroborating
Government authority (1)
- New $2 billion tech hub for Fishermans Bend · Jun 12, 2025 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Investment commitment
A$2,000,000,000Jun 12, 2025
NEXTDC project commitment; no separate debt/equity package disclosed.
Parties & sources
NEXTDC Limited (Sponsor)
Sources (2)
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (5)
Planned or represented
150 MW
target it capacity — 150 MW; planned.
Planned or represented
direct to chip liquid cooling; planned.
Planned or represented
recycled water cooling; planned.
Planned or represented
onsite solar and microgrid; planned.
Planned or represented
waste heat recovery; planned.
Project map
Building · Issued
M4 Technology Campus
Victorian Government
Jan 19, 2026
Sources (1)
- M4 Technology Campus approved · Jan 19, 2026 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (1)
Partially operational · West Footscray, Victoria, Australia
Shared participant: NEXTDC Limited · Same market: Victoria, Australia