VIRTUS Marienpark Campus

Berlin, GermanyUnder construction
Capacity
57.6 MW
Planned critical IT
Lead participant
VIRTUS Data Centres
Developer
Last updated
Aug 29, 2026
Most recent public record update

About VIRTUS Marienpark Campus

VIRTUS Marienpark is a four-building Berlin campus under construction, with 14.4 MW per building and 57.6 MW at full delivery. Standard Chartered’s €210 million green financing is recorded as campus construction funding, not a facility valuation. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load57.6 MWDesign · VIRTUS Marienpark Campus
Future Potential57.6 MWDesign · VIRTUS Marienpark Campus

Development

1 phases · 3 milestones
Development, permitting and phased deliveryUnder Construction

VIRTUS Marienpark is a four-building Berlin campus under construction, with 14.4 MW per building and 57.6 MW at full delivery. Standard Chartered’s €210 million green financing is recorded as campus construction funding, not a facility valuation. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Jun 1, 2025
Marienpark campus broke ground
Completed
Feb 5, 2026
€210 million green financing closed
Completed
Aug 29, 2026
Project-specific source review refreshed
Completed

Infrastructure

Electric GridOperational

57.6 MW

57.6 MW is the operator-published facility IT-load boundary; it is not measured customer utilization.

FiberOperational

Carrier-neutral or resilient fibre connectivity is described for the individual facility.

Cooling SystemOperational

Cooling architecture supports the stated lifecycle; actual tenant draw and instantaneous load remain undisclosed.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Cooling & water: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

18 facts
Location Context
VIRTUS Marienpark | Berlin | Berlin | DE
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
57.6 MW
Design
Capacity Basis
VIRTUS Data Centres publishes 57.6 MW for this project boundary.
Actual
Location Context
VIRTUS Marienpark | Berlin | Berlin | DE
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
57.6 MW
Design
Capacity Basis
57.6 MW is the published future facility or full build IT boundary; it is not operating load.
Actual
Operator Confirmed
VIRTUS Data Centres
Actual
Project Location
Berlin, Berlin, DE
Actual
Current Lifecycle
Partly operating with phased delivery or expansion underway
Actual
Capacity Classification
Future potential
Actual
Capacity Basis
57.6 MW is the operator published facility IT-load boundary; it is not measured customer utilization.
Actual
Customer Utilization
Not publicly disclosed
Actual
Identity Boundary
This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios
Actual
Source Refresh Date
2026-08-29
Actual
Facility Count
4
Design
Green Financing
€210,000,000
Closed Financing