NTT DATA Berlin 2 Data Center Campus

Berlin, BE, GermanyPartially operational
Capacity
24 MW
Planned / design
Lead participant
NTT DATA
Developer
Last updated
Aug 28, 2026
Most recent public record update

About NTT DATA Berlin 2 Data Center Campus

NTT DATA Berlin 2 Data Center Campus, also known as NTT Berlin 2, is a data center project in Berlin, BE, DE associated with NTT DATA. Two-building campus; 10,000 square metres; 24 MW published critical IT load. Berlin campus developed as two carrier-connected high-availability buildings.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load24 MWDesign · NTT DATA Berlin 2 Data Center Campus
Design24 MWDesign · NTT DATA Berlin 2 Data Center Campus

Development

1 phases · 2 milestones
Operating facility and documented expansionPartially Operational

24 MW is the operator-published facility or campus design boundary. It is not measured tenant utilization or live IT draw.

Sep 1, 2021
Current source record reviewed for NTT Berlin 2
Completed
Aug 30, 2026
Operating boundary reviewed without inferring tenant utilization
Completed

Infrastructure

Electric GridEnergized

Berlin campus developed as two carrier-connected high-availability buildings.

Cooling SystemOperational

Cooling and efficiency claims remain limited to operator-described designs; no water use or delivered load is inferred.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

13 facts
Location Context
NTT Berlin 2 | Berlin | BE | DE
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
24 MW
Design
Capacity Basis
NTT DATA publishes 24 MW of critical IT capacity for this record boundary.
Actual
Location Context
NTT Berlin 2 | Berlin | BE | DE
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
24 MW
Design
Capacity Basis
24 MW facility or campus design capacity.
Actual
Project Identity
NTT Berlin 2
Actual
Location Context
Berlin, BE, DE
Actual
Lifecycle Status
Partially operational
Actual
Development Detail
Two building campus; 10,000 square metres; 24 MW published critical IT load.
Actual
Capacity Basis
24 MW facility or campus design capacity.