Cartis diligence evidence schedule

VIRTUS Marienpark Campus

PRJ-1000 · Site · Berlin, Germany

Record last updated Oct 28, 2026

Scope and capacity

VIRTUS Marienpark is a four-building Berlin campus under construction, with 14.4 MW per building and 57.6 MW at full delivery. Standard Chartered’s €210 million green financing is recorded as campus construction funding, not a facility valuation. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Headline: 57.6 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (18)

Location context · VIRTUS Marienpark | Berlin | Berlin | DE

Actual · VIRTUS Marienpark Campus (Project)

Claim 67272 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Lifecycle status · Partially operational

Actual · VIRTUS Marienpark Campus (Project)

Claim 67273 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Reported capacity · 57.6 MW

Design · VIRTUS Marienpark Campus (Project)

Claim 67274 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Capacity basis · VIRTUS Data Centres publishes 57.6 MW for this project boundary.

Actual · VIRTUS Marienpark Campus (Project)

Claim 67275 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Location context · VIRTUS Marienpark | Berlin | Berlin | DE

Actual · VIRTUS Marienpark Campus (Project)

Claim 84829 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Lifecycle status · Construction

Actual · VIRTUS Marienpark Campus (Project)

Claim 84830 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Reported capacity · 57.6 MW

Planned / design or future potential · VIRTUS Marienpark Campus (Project)

Claim 84831 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Capacity basis · 57.6 MW is the published future facility or full build IT boundary; it is not operating load.

Actual · VIRTUS Marienpark Campus (Project)

Claim 84832 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Operator confirmed · VIRTUS Data Centres

Actual · VIRTUS Marienpark Campus (Project)

Claim 84833 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Project location · Berlin, Berlin, DE

Actual · VIRTUS Marienpark Campus (Project)

Claim 84834 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Current lifecycle · Partly operating with phased delivery or expansion underway

Actual · VIRTUS Marienpark Campus (Project)

Claim 84835 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Capacity classification · Future potential

Actual · VIRTUS Marienpark Campus (Project)

Claim 84836 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Capacity basis · 57.6 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · VIRTUS Marienpark Campus (Project)

Claim 84837 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Customer utilization · Not publicly disclosed

Actual · VIRTUS Marienpark Campus (Project)

Claim 84838 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Identity boundary · This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios

Actual · VIRTUS Marienpark Campus (Project)

Claim 84839 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark green financing

    Standard Chartered · Document date: Feb 5, 2026 · Primary

    Source reference: SRC-4771 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.sc.com/de-en/2026/02/05/virtus-data-centres-marienpark/

Source refresh date · 2026-08-29

Actual · VIRTUS Marienpark Campus (Project)

Claim 84840 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Facility count · 4 buildings

Design · VIRTUS Marienpark Campus (Project)

Claim 84841 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark Campus official profile

    VIRTUS Data Centres · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3821 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://virtusdatacentres.com/locations/marienpark-campus

Green financing · €210,000,000

Closed financing · VIRTUS Marienpark Campus (Project)

Claim 84843 · Recorded claim type: Closed financing · Review: Approved · Claim date: Not stated

  1. VIRTUS Marienpark green financing

    Standard Chartered · Document date: Feb 5, 2026 · Primary

    Source reference: SRC-4771 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.sc.com/de-en/2026/02/05/virtus-data-centres-marienpark/

Counterparties and capital

VIRTUS Data Centres · Developer · CMP-1121

Debt financing

€210,000,000 · Feb 5, 2026

Four-building Marienpark campus financing arranged by Standard Chartered.

VIRTUS Data Centres (Borrower)

Sources (1)

Financing record 180; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.