Skip to content

VIRTUS London 1 Enfield Data Centre

Enfield, England, United KingdomOperating
Evidence
Planned critical IT
4.2 MW
Updated
Oct 28, 2026

VIRTUS London 1 Enfield Data Centre is the operating LONDON1 Enfield facility. Its 4.2 MW IT boundary and exact facility code are preserved, preventing a merge with larger VIRTUS campuses or newer London-numbered buildings. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Capacity

Reported capacity

Design

4.2 MW

Source

Reported capacity

Design

4.2 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionOperational

VIRTUS London 1 Enfield Data Centre is the operating LONDON1 Enfield facility. Its 4.2 MW IT boundary and exact facility code are preserved, preventing a merge with larger VIRTUS campuses or newer London-numbered buildings. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Participants

VIRTUS Data Centres

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

VIRTUS LONDON1 | Enfield | England | GB

Source

Location context

Actual

VIRTUS LONDON1 | Enfield | England | GB

Source

Project location

Actual

Enfield, England, GB

Source

Additional project facts

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

VIRTUS Data Centres publishes 4.2 MW for this project boundary.

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

4.2 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Source

Operator confirmed

Actual

VIRTUS Data Centres

Source

Current lifecycle

Actual

Operating

Source

Capacity classification

Actual

It load

Source

Capacity basis

Actual

4.2 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Source

Customer utilization

Actual

Not publicly disclosed

Source

Identity boundary

Actual

This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios

Source

Source refresh date

Actual

2026-08-29

Source

Facility code

Actual

LONDON1

Source

Independent address confirmation

Actual

Confirmed by independent operations register

Source

Infrastructure & permits

Technical details (3)
Electric grid

Operational

4.2 MW

4.2 MW is the operator-published facility IT-load boundary; it is not measured customer utilization.

Fiber

Operational

Carrier-neutral or resilient fibre connectivity is described for the individual facility.

Cooling system

Operational

Cooling architecture supports the stated lifecycle; actual tenant draw and instantaneous load remain undisclosed.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (4)
VIRTUS London 2 Hayes Data Centre

Operating · Hayes, England, United Kingdom

Shared participant: VIRTUS Data Centres · Same market: England, United Kingdom

Compare in a collection
VIRTUS LONDON19 Slough

Preconstruction · Slough, England, United Kingdom

Shared participant: VIRTUS Data Centres · Same market: England, United Kingdom

Compare in a collection
VIRTUS Saunderton Campus

Partially operational · Saunderton, England, United Kingdom

Shared participant: VIRTUS Data Centres · Same market: England, United Kingdom

Compare in a collection
VIRTUS Slough Campus

Partially operational · Slough, England, United Kingdom

Shared participant: VIRTUS Data Centres · Same market: England, United Kingdom

Compare in a collection