STT Chennai 2 Data Center

Chennai, Tamil Nadu, IndiaOperating / Stabilized
Capacity
No public figure
Lead participant
STT GDC India
Developer
Last updated
Aug 28, 2026
Most recent public record update

About STT Chennai 2 Data Center

STT Chennai 2 Data Center is a separately tracked operating STT GDC facility in Chennai, Tamil Nadu, IN. The current operator catalog states 25.5 MW of IT load for this building; Planned values are presented as future facility boundaries and operating values as installed capacity, not measured tenant draw. Independent Chennai evidence supports the physical campus and lifecycle context without transferring portfolio totals to this record.

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

1 phases · 2 milestones
Operating facility and documented expansionOperational

STT Chennai 2 Data Center is a separately tracked operating STT GDC facility in Chennai, Tamil Nadu, IN. The current operator catalog states 25.5 MW of IT load for this building; Planned values are presented as future facility boundaries and operating values as installed capacity, not measured tenant draw. Independent Chennai evidence supports the physical campus and lifecycle context without transferring portfolio totals to this record. The available public sources do not establish a single project-scoped capacity figure.

Aug 29, 2026
Project-specific source review refreshed
Completed
Aug 29, 2026
Exact 25.5 MW value held for reconciliation with current >20 MW source wording
Completed

Infrastructure

Electric GridOperational

25.5 MW

Facility IT boundary; customer utilization is not disclosed.

FiberOperational

Carrier-neutral or resilient fibre connectivity described for the individual facility.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

13 facts
Location Context
STT Chennai 2 | Chennai | Tamil Nadu | IN
Actual
Lifecycle Status
Operating
Actual
Capacity Basis
STT GDC India publishes 25.5 MW of IT load for this facility.
Actual
Location Context
STT Chennai 2 | Chennai | Tamil Nadu | IN
Actual
Lifecycle Status
Operating
Actual
Operator Confirmed
STT GDC India
Actual
Facility Capacity Basis
The stored 25.5 MW value is not reconciled with the current operator description of more than 20 MW; headline withheld pending an exact current IT figure.
Actual
Current Lifecycle
Operating
Actual
Evidence Boundary
Facility specific evidence; campus or portfolio figures are not transferred between records
Actual
Regional Platform
Chennai
Actual
Capacity Unit
IT load
Actual
Customer Utilization
Not publicly disclosed
Actual
Certification
TIA-942 Rated 3 and LEED Gold