Skip to content
All records
Data center siteSite record

STACK Stafford Technology Campus

Stafford, Virginia, United StatesPreconstruction
Capacity
1,100 MW
Planned / design
Lead participant
STACK Infrastructure
Developer
Last updated
Aug 28, 2026
Most recent public record update

About STACK Stafford Technology Campus

STACK Stafford Technology Campus, also known as Stafford Technology Campus, is a data center project in Stafford, VA, US developed and operated by STACK Infrastructure. 500-acre master-planned campus organized into four sub-campuses with 19 data centers and more than 1 GW of capacity. Six planned 300 MW substations, multiple utility feeds, four diverse fiber paths and closed-loop cooling designed for high-density AI workloads. 1.1 GW is the current planned full-build campus envelope supported by six planned 300 MW substations; no portion is represented as operating IT load.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load1,000 MWDesign · STACK Stafford Technology Campus
Future Potential1,100 MWDesign · STACK Stafford Technology Campus

Development

1 phases · 2 milestones
Development, permitting and phased deliveryAnnounced Or Preconstruction

1.1 GW is the current planned full-build campus envelope supported by six planned 300 MW substations; no portion is represented as operating IT load.

Jan 16, 2025
STACK announced 1 GW+ Stafford Technology Campus
Completed
Oct 1, 2025
STACK documented $58 million regional water commitment
Completed

Infrastructure

Electric GridPlanned Or Represented

Six planned 300 MW substations, multiple utility feeds, four diverse fiber paths and closed-loop cooling designed for high-density AI workloads.

FiberPlanned Or Represented

STACK markets diverse fiber and carrier-neutral deployment options; installed and contracted capacity remain distinct.

WaterPlanned Or Represented

$58,000,000

Regional reclaimed-water and purple-pipe improvements; campus industrial cooling is planned without potable water.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Cooling & water: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Stafford Technology Campus | Stafford | VA | US
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
1,000 MW
Design
Capacity Basis
STACK Infrastructure publishes 1000 MW of critical IT capacity for this record boundary.
Actual
Location Context
Stafford Technology Campus | Stafford | VA | US
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
1,100 MW
Design
Capacity Basis
1.1 GW is the current planned full build campus envelope supported by six planned 300 MW substations; no portion is represented as operating IT load.
Actual
Site Area
500 acres
Design
Subcampuses
4 subcampuses
Design
Data Centers
19
Design
Planned Substations
6 substations
Design