STACK MIL04 Pavia Data Center Campus

Pavia, Lombardy, ItalyPartially operational
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

STACK MIL04 is the four-building Vellezzo Bellini campus in Pavia. Building cards total 64 MW, while current campus prose and the independent register describe 60 MW. Cartis publishes the location, four-building plan and infrastructure context but withholds the headline until STACK reconciles the campus total. The capacity or identity headline remains held until the named conflict is resolved; no automatic merge is authorized.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionOperational

STACK MIL04 is the four-building Vellezzo Bellini campus in Pavia. Building cards total 64 MW, while current campus prose and the independent register describe 60 MW. Cartis publishes the location, four-building plan and infrastructure context but withholds the headline until STACK reconciles the campus total. The capacity or identity headline remains held until the named conflict is resolved; no automatic merge is authorized.

Milestones (1)
Project-specific evidence refreshed and reconciled

Aug 29, 2026 · Recorded actual event

Completed · Status changed

Source not linked

Participants

STACK Infrastructure

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

STACK MIL04 | Pavia | Lombardy | IT

Source

Location context

Actual

STACK MIL04 | Pavia | Lombardy | IT

Source

Project location

Actual

Pavia, Lombardy, IT

Source

Building count

Design

4 buildings

Source

Additional project facts

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

STACK Infrastructure publishes 64 MW of critical IT capacity for this record boundary.

Source

Lifecycle status

Actual

Partially operational

Source

Operator or developer

Actual

STACK Infrastructure

Source

Current lifecycle

Actual

Operating or in phased operation

Source

Capacity classification

Actual

Design

Source

Capacity basis

Actual

The four published building figures sum to 64 MW, while current independent and first party campus prose also says 60 MW. The headline is withheld pending a reconciled operator specification.

Source

Customer utilization

Actual

Not publicly disclosed

Source

Source refresh date

Actual

2026-08-29

Source

Published capacity conflict

Reported rounded

60–64 MW

Source

Infrastructure & permits

Technical details (3)
Electric grid

Operational

The four published building figures sum to 64 MW, while current independent and first-party campus prose also says 60 MW. The headline is withheld pending a reconciled operator specification.

Fiber

Operational

Dedicated campus power and connectivity with four buildings ranging from 10 MW to 24 MW.

Cooling system

Operational

Cooling and resilience architecture is described at facility or campus level; instantaneous draw and tenant utilization remain undisclosed.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (4)
STACK MIL07 Pavia Data Center Campus

Preconstruction · Pavia, Lombardy, Italy

Same locality: Pavia · Shared participant: STACK Infrastructure

Compare in a collection
STACK MIL02 Milan Data Center Campus

Partially operational · Milan, Lombardy, Italy

Shared participant: STACK Infrastructure · Same market: Lombardy, Italy

Compare in a collection
STACK MIL03 Milan Data Center Campus

Partially operational · Milan, Lombardy, Italy

Shared participant: STACK Infrastructure · Same market: Lombardy, Italy

Compare in a collection
STACK MIL05 Milan Data Center Campus

Preconstruction · Milan, Lombardy, Italy

Shared participant: STACK Infrastructure · Same market: Lombardy, Italy

Compare in a collection