STACK MIL02 Milan Data Center Campus

Milan, Lombardy, ItalyPartially operational
Capacity
No public figure
Lead participant
STACK Infrastructure
Developer
Last updated
Aug 28, 2026
Most recent public record update

About STACK MIL02 Milan Data Center Campus

STACK MIL02A is the Via Marche 9 facility opened in July 2022. Current transaction and facility records suggest that the colocation asset may now sit within the adjacent Vaultica MIL01 campus boundary, but the public evidence does not provide a clean one-to-one successor mapping. The available evidence does not establish a clean one-to-one successor mapping, so the possible consolidation remains unresolved. The named capacity or identity conflict remains unresolved.

Projects sharing a market, utility, or organization.

4 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

1 phases · 1 milestones
Operating facility and documented expansionOperational

STACK MIL02A is the Via Marche 9 facility opened in July 2022. Current transaction and facility records suggest that the colocation asset may now sit within the adjacent Vaultica MIL01 campus boundary, but the public evidence does not provide a clean one-to-one successor mapping. The available evidence does not establish a clean one-to-one successor mapping, so the possible consolidation remains unresolved. The named capacity or identity conflict remains unresolved.

Aug 29, 2026
Project-specific evidence refreshed and reconciled
Completed

Infrastructure

Electric GridOperational

MIL02A is a distinct legacy STACK identity, but current M&A records indicate the operating asset may now be consolidated into Vaultica MIL01. The available public sources do not establish a single project-scoped capacity figure.

FiberOperational

Dedicated high-voltage substation and proximity to major Milan-area highways.

Cooling SystemOperational

Cooling and resilience architecture is described at facility or campus level; instantaneous draw and tenant utilization remain undisclosed.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1Cooling & water: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

14 facts
Location Context
STACK MIL02 | Milan | Lombardy | IT
Actual
Lifecycle Status
Partially operational
Actual
Capacity Basis
STACK Infrastructure publishes 5.6 MW of critical IT capacity for this record boundary.
Actual
Location Context
STACK MIL02 | Milan | Lombardy | IT
Actual
Lifecycle Status
Partially operational
Actual
Operator Or Developer
STACK Infrastructure
Actual
Project Location
Milan, Lombardy, IT
Actual
Current Lifecycle
Operating or in phased operation
Actual
Capacity Classification
Design
Actual
Capacity Basis
MIL02A is a distinct legacy STACK identity, but current M&A records indicate the operating asset may now be consolidated into Vaultica MIL01.
Actual
Customer Utilization
Not publicly disclosed
Actual
Source Refresh Date
2026-08-29
Actual
Opened
2022-07
Actual
Identity Merge Candidate
Possible consolidation into Vaultica MIL01
Actual