Project Kilby Power Facility
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
Project Kilby's current operator timeline, checked October 28, 2026, forecasts full capacity in 2031, distinct from first power targeted for 2028. National Grid's July 1, 2026 announcement of a US$1.75 billion investment for a 35% stake in Joulent is company-level funding supporting development, not an allocation of that entire amount to Kilby construction. Co-located Energy Forge One generation facility contracted to serve Microsoft Pecos; generation capacity is not campus IT capacity. Project Kilby Power Facility is located in Pecos area, TX, US and is a generation site in preconstruction status.
Capacity
Planned generation capacity
Planned / design or future potential2.67 GW
Generation capacity; not IT capacity
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Phased modular generation; individual blocks are not modeled without a public schedule.
Milestones (4)
Dec 2, 2025 · Recorded actual event
Completed · Event type not stated
Source not linkedJun 22, 2026 · Recorded actual event
Completed · Customer commitment
Source not linked2026 · Forecast / planned record
Forecast · Event type not stated
Source not linked2028 · Forecast / planned record
Forecast · Commercial operation
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Chevron signs 20-year power agreement with Microsoft for West Texas data center · Jun 22, 2026 · Primary
Developer (1)
- Energy Forge One JETI application supplement · Dec 2, 2025 · Corroborating
Customer
Sources by role
Customer (1)
- Chevron signs 20-year power agreement with Microsoft for West Texas data center · Jun 22, 2026 · Primary
Customer (1)
- Chevron signs power supply deal with Microsoft for Texas data center · Jun 22, 2026 · Corroborating
Other participants (2)
Supplier
Sources by role
Supplier (1)
- Chevron signs 20-year power agreement with Microsoft for West Texas data center · Jun 22, 2026 · Primary
Supplier
Sources by role
Supplier (1)
- Chevron signs 20-year power agreement with Microsoft for West Texas data center · Jun 22, 2026 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
20-year power purchase agreement
Amount not disclosedJun 22, 2026
Long-term power agreement between Energy Forge One and Microsoft; price and committed offtake undisclosed.
Parties & sources
Chevron (Parent sponsor) · Energy Forge One LLC (Power seller) · Microsoft (Power buyer)
Sources (2)
Incentives
Incentive
Status not stated · Texas Comptroller of Public Accounts
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (1)
Planned or represented
2.67 GW
Phased modular generation; FID pending and first power targeted 2028.
Project map
Permit · Status not stated
Project Kilby / Energy Forge One
Texas Comptroller of Public Accounts
Dec 2, 2025
Sources (1)
- Energy Forge One JETI application supplement · Dec 2, 2025 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (4)
Operating · Abilene, Texas, United States
Shared participant: GE Vernova · Shared participant: Solar Turbines · Same market: Texas, United States
Compare in a collectionPreconstruction · Abilene, Texas, United States
Shared participant: Microsoft · Same market: Texas, United States
Compare in a collectionPartially operational · Childress, Texas, United States
Shared participant: Microsoft · Same market: Texas, United States
Compare in a collectionPreconstruction · Pecos, Texas, United States
Shared participant: Microsoft · Same market: Texas, United States
Compare in a collection