Project Kilby Power Facility

Pecos area, Texas, United StatesPreconstruction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Project Kilby's current operator timeline, checked October 28, 2026, forecasts full capacity in 2031, distinct from first power targeted for 2028. National Grid's July 1, 2026 announcement of a US$1.75 billion investment for a 35% stake in Joulent is company-level funding supporting development, not an allocation of that entire amount to Kilby construction. Co-located Energy Forge One generation facility contracted to serve Microsoft Pecos; generation capacity is not campus IT capacity. Project Kilby Power Facility is located in Pecos area, TX, US and is a generation site in preconstruction status.

Capacity

Planned generation capacity

Planned / design or future potential

2.67 GW

Generation capacity; not IT capacity

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Project Kilby generation buildAnnounced or preconstruction

Phased modular generation; individual blocks are not modeled without a public schedule.

Milestones (4)
Energy Forge One application supplement dated

Dec 2, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked
Chevron announces Microsoft power agreement

Jun 22, 2026 · Recorded actual event

Completed · Customer commitment

Source not linked
Project Kilby targets final investment decision by year-end 2026

2026 · Forecast / planned record

Forecast · Event type not stated

Source not linked
Project Kilby targets first power in 2028

2028 · Forecast / planned record

Forecast · Commercial operation

Source not linked

Participants

Energy Forge One LLC

Developer

Sources by role
Developer (1)
Developer (1)
Microsoft

Customer

Sources by role
Other participants (2)
GE Vernova

Supplier

Sources by role
Solar Turbines

Supplier

Sources by role

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Final investment decision target

Actual

2026 Year end

Source

Estimated state local tax revenue greater than

Actual

$10 billion

Source

Financing records

20-year power purchase agreement

Amount not disclosed

Jun 22, 2026

Long-term power agreement between Energy Forge One and Microsoft; price and committed offtake undisclosed.

Parties & sources

Chevron (Parent sponsor) · Energy Forge One LLC (Power seller) · Microsoft (Power buyer)

Incentives

Incentive

Status not stated · Texas Comptroller of Public Accounts

Site & development

Development configuration

Actual

Phased and modular

Source

Construction jobs approximately

Actual

2,000 jobs

Source

Technical specifications

Power agreement term

Actual

20 years

Source

First power target year

Actual

2028

Source

Generation fuel

Actual

Natural gas

Source

Planned primary water source

Actual

Non potable brackish water

Source

Produced water option under review

Actual

True

Source

Additional project facts

Majority equipment supplier

Actual

GE Vernova

Source

Additional equipment supplier

Actual

Solar Turbines

Source

Selective catalytic reduction planned

Actual

True

Source

Infrastructure & permits

Technical details (1)
Onsite natural gas generation

Planned or represented

2.67 GW

Phased modular generation; FID pending and first power targeted 2028.

Permit · Status not stated

Project Kilby / Energy Forge One

Texas Comptroller of Public Accounts

Dec 2, 2025

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (4)
Stargate Abilene

Operating · Abilene, Texas, United States

Shared participant: GE Vernova · Shared participant: Solar Turbines · Same market: Texas, United States

Compare in a collection
Crusoe–Microsoft Abilene

Preconstruction · Abilene, Texas, United States

Shared participant: Microsoft · Same market: Texas, United States

Compare in a collection
IREN Childress Horizon AI Data Center Campus

Partially operational · Childress, Texas, United States

Shared participant: Microsoft · Same market: Texas, United States

Compare in a collection
Microsoft Pecos AI Datacenter Campus

Preconstruction · Pecos, Texas, United States

Shared participant: Microsoft · Same market: Texas, United States

Compare in a collection