Nebius Highridge AI Campus

Highridge Business Park, Butler Township, Pennsylvania, United StatesPreconstruction
Capacity
No public figure
Lead participant
Nebius
Operator
Last updated
Aug 26, 2026
Most recent public record update

About Nebius Highridge AI Campus

Nebius is developing an owned AI data center campus at Highridge Business Park in Schuylkill County. Public plans describe about 600 acres, six buildings and phased power scaling from a 260 MW initial phase toward a 1.2 GW full-build envelope.

Projects sharing a market, utility, or organization.

1 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design660 MWForecast · 660 MW cumulative state

Development

3 phases · 4 milestones
Initial 260 MW phaseAnnounced Or Preconstruction

Named initial phase; capacity basis is described only as campus capacity/power and is not normalized to IT load.

660 MW cumulative statePlanned

Cumulative campus state, not an additional 660 MW phase.

Full-build campusPlanned

Six single-story buildings appear in reported site plans; no building-level names or capacities are created.

6 buildings

May 1, 2026
Reported $187.5 million Highridge land closing
Completed
May 13, 2026
Nebius announces Pennsylvania AI factory
Completed
Oct 1, 2027
Initial phase operating target
Forecast
Dec 31, 2029
660 MW cumulative target
Forecast

Infrastructure

Electric GridPlanned Or Represented

1.2 GW

Nebius secured up to 1.2 GW of power and land; detailed campus plan describes 1.2 GW at full buildout. Capacity basis is not disclosed as IT load.

Electric GridPlanned Or Represented

260 MW

Initial phase expected operational by October 2027; treated as planned campus/power capacity, not operating IT load.

Electric GridPlanned Or Represented

660 MW

Potential cumulative campus state by 2029, not a separate additive phase.

Utility ServiceSecured Or Contracted

Dedicated energy service agreement reported for the project; delivery schedule and service voltage are undisclosed.

Battery StoragePlanned Or Represented

30 minutes

BESS described as approximately 30 minutes of backup and redundant power during an outage; energy and power ratings undisclosed.

Cooling SystemPlanned Or Represented

Both air and liquid cooling with closed-loop cooling intended to reduce water use.

Project map

0 of 1 project point mapped
Infrastructure facts
6
Mapped records
1
Capacity figures
4

No map point available

Power & interconnection: 4Generation & storage: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

12 facts
Location
Highridge Business Park, Butler Township, Schuylkill County, Pennsylvania
Actual
Site Area
600 acres approx
Forecast
Building Count
6 single story buildings
Design
Ownership
Fully owned and operated by Nebius
Forecast
Target Operational Date
2027-10
Forecast
Capacity
660 MW
Forecast
Target Date
2029
Forecast
Later Capacity
1+ GW
Forecast
Electric Service
Dedicated energy service agreement with PPL Electric Utilities
Actual
Backup Duration
30 minutes approx
Forecast
Cooling
Air and liquid cooling
Design
Water Strategy
Closed loop cooling intended to reduce water use
Design