Cartis diligence evidence schedule
Nebius Highridge AI Campus
PRJ-0549 · Site · Highridge Business Park, Butler Township, Pennsylvania, United States
Record last updated Oct 28, 2026
Scope and capacity
Nebius is developing an owned AI data center campus at Highridge Business Park in Schuylkill County. Public plans describe about 600 acres, six buildings and phased power scaling from a 260 MW initial phase toward a 1.2 GW full-build envelope.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location · Highridge Business Park, Butler Township, Schuylkill County, Pennsylvania
Actual · Nebius Highridge AI Campus (Project)
Claim 50480 · Recorded claim type: Actual · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
- Schuylkill Economic Development Corporation home page
SEDCO · Document date: Not stated · Corroborating
Source reference: SRC-2655 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sed-co.com/
https://www.sed-co.com/
Site area · 600 acres approx
Forecast · Nebius Highridge AI Campus (Project)
Claim 50481 · Recorded claim type: Forecast · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Building count · 6 single story buildings
Design · Nebius Highridge AI Campus (Project)
Claim 50482 · Recorded claim type: Design · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Ownership · Fully owned and operated by Nebius
Forecast · Nebius Highridge AI Campus (Project)
Claim 50483 · Recorded claim type: Forecast · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Corroborating
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
- Nebius reports first quarter 2026 financial results
Nebius · Document date: May 13, 2026 · Primary
Source reference: SRC-2653 · Company announcement · Recorded authority: Party primary
Source URL
https://nebius.com/newsroom/nebius-reports-first-quarter-2026-financial-results
https://nebius.com/newsroom/nebius-reports-first-quarter-2026-financial-results
Target operational date · 2027-10
Forecast · Initial 260 MW phase (Phase)
Claim 50486 · Recorded claim type: Forecast · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Capacity · 660 MW
Planned / design or future potential · 660 MW cumulative state (Phase)
Claim 50487 · Recorded claim type: Forecast · Review: Approved · Claim date: Jul 27, 2026
Headline treatment: Phase scope; not a whole-site figure
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Target date · 2029
Forecast · 660 MW cumulative state (Phase)
Claim 50488 · Recorded claim type: Forecast · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Later capacity · 1+ GW
Planned / design or future potential · Full-build campus (Phase)
Claim 50489 · Recorded claim type: Forecast · Review: Approved · Claim date: Jul 27, 2026
Headline treatment: Phase scope; not a whole-site figure
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Electric service · Dedicated energy service agreement with PPL Electric Utilities
Actual · Nebius Highridge AI Campus (Project)
Claim 50490 · Recorded claim type: Actual · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Backup duration · 30 minutes approx
Forecast · Nebius Highridge AI Campus (Project)
Claim 50491 · Recorded claim type: Forecast · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Cooling · Air and liquid cooling
Design · Nebius Highridge AI Campus (Project)
Claim 50492 · Recorded claim type: Design · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Water strategy · Closed loop cooling intended to reduce water use
Design · Nebius Highridge AI Campus (Project)
Claim 50493 · Recorded claim type: Design · Review: Approved · Claim date: Jul 27, 2026
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: Jul 27, 2026 · Primary
Source reference: SRC-2654 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Counterparties and capital
Butler Township · Government authority · CMP-1263
Nebius · Operator · CMP-0120
PPL Electric Utilities · Utility provider · CMP-1117
Schuylkill Economic Development Corporation · Government authority · CMP-1262
$187,500,000 · May 1, 2026
Reported transaction amount; not a construction-financing commitment.
Nebius (Other)
Sources (1)
Financing record 143; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.