Nebius Highridge AI Campus
PRJ-0549 · Site · Highridge Business Park, Butler Township, Pennsylvania, United States
Captured 2026-09-06T04:13:04.163Z · Record last updated 2026-08-26
SHA-256: c72ea70a93855561d8778a2ff8618c9e8fd53e362744705c19531b8707fc7be0
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
Nebius is developing an owned AI data center campus at Highridge Business Park in Schuylkill County. Public plans describe about 600 acres, six buildings and phased power scaling from a 260 MW initial phase toward a 1.2 GW full-build envelope.
Headline: —
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Location · Highridge Business Park, Butler Township, Schuylkill County, Pennsylvania
actual · Nebius Highridge AI Campus (project)
Claim 50480 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/ - Schuylkill Economic Development Corporation home page
SEDCO · Document date: Not published · Corroborating
https://www.sed-co.com/
Site Area · 600 acres approx
forecast · Nebius Highridge AI Campus (project)
Claim 50481 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Building Count · 6 single story buildings
design · Nebius Highridge AI Campus (project)
Claim 50482 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Ownership · Fully owned and operated by Nebius
forecast · Nebius Highridge AI Campus (project)
Claim 50483 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Corroborating
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/ - Nebius reports first quarter 2026 financial results
Nebius · Document date: 2026-05-13 · Primary
https://nebius.com/newsroom/nebius-reports-first-quarter-2026-financial-results
Target Operational Date · 2027-10
Planned / design or future potential · Initial 260 MW phase (phase)
Claim 50486 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Capacity · 660 MW
Planned / design or future potential · 660 MW cumulative state (phase)
Claim 50487 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
Headline treatment: Phase scope; not a whole-site figure
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Target Date · 2029
Planned / design or future potential · 660 MW cumulative state (phase)
Claim 50488 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Later Capacity · 1+ GW
forecast · Full-build campus (phase)
Claim 50489 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Electric Service · Dedicated energy service agreement with PPL Electric Utilities
actual · Nebius Highridge AI Campus (project)
Claim 50490 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Backup Duration · 30 minutes approx
forecast · Nebius Highridge AI Campus (project)
Claim 50491 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Cooling · Air and liquid cooling
design · Nebius Highridge AI Campus (project)
Claim 50492 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Water Strategy · Closed loop cooling intended to reduce water use
design · Nebius Highridge AI Campus (project)
Claim 50493 · Review: Approved · Claim date: 2026-07-27T00:00:00+00:00
- Nebius details plans for 1.2GW data center campus in Pennsylvania
Data Center Dynamics · Document date: 2026-07-27 · Primary
https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/
Counterparties and capital
Butler Township · Government Authority · CMP-1263
Nebius · Operator · CMP-0120
PPL Electric Utilities · Utility Provider · CMP-1117
Schuylkill Economic Development Corporation · Government Authority · CMP-1262
$187,500,000 · 2026-05-01
Reported transaction amount; not a construction-financing commitment.
Nebius (Other)
Financing record 143; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.