PowerHouse Data Centers Carlisle
Preconstruction · Carlisle, Pennsylvania, United States
Pennsylvania Digital I (PAX) Program covers shared infrastructure and three distinct campus stages; 1.35/1.8 GW are utility envelopes, planned utility capacity.
Projects sharing a market, utility, or organization.
Preconstruction · Carlisle, Pennsylvania, United States
Preconstruction · Highridge Business Park, Butler Township, Pennsylvania, United States
Current sponsor page allocates the first power step to Q4 2027; state page still cites Q2 2027. Current five-to-six-building campus range is not assigned more precisely.
Current sponsor schedule reaches 900 MW aggregate by Q2 2028. Current five-to-six-building campus range is not assigned more precisely.
Current sponsor schedule reaches 1,350 MW aggregate by Q2 2029. Current five-to-six-building campus range is not assigned more precisely.
Up to 1.8 GW future utility envelope; physical allocation undisclosed.
1,350 MW
500 kV-to-138 kV switching station and three 450 MW dedicated campus substations; expandable utility envelope to 1.8 GW.
17 metro networks
Announced access to 17 metro fiber networks including direct Ashburn peering.
No map point available
Published claims and their source links.