Meta New Albany Prometheus AI Data Center Campus

New Albany, Ohio, United StatesUnder construction
Capacity
1,000 MW
Planned / design
Lead participant
Meta Platforms, Inc.
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Meta New Albany Prometheus AI Data Center Campus

Meta is expanding its New Albany campus into a gigawatt-scale AI facility associated with the Prometheus supercluster. The disclosed 1 GW figure is the capacity expected once construction is complete. Meta is publicly identified in the project record for New Albany, Licking County area, OH, US. The disclosed development record includes meta identifies New Albany as one of its facilities expected to reach at least 1 GW after construction; the campus originally broke ground in 2017. Power and infrastructure include large multi-building AI-optimized campus with continuing power, cooling and network expansion. Meta states the New Albany facility will have at least 1 GW of capacity once construction is complete.

Projects sharing a market, utility, or organization.

3 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design1,000 MWDesign · Meta New Albany Prometheus AI Data Center Campus

Development

1 phases · 2 milestones
Construction programUnder Construction

Project-wide phase for Meta New Albany Prometheus AI Data Center Campus; capacity remains classified as design.

Apr 1, 2026
Meta New Albany project status and capacity disclosed
Completed
Operational campus with gigawatt-scale AI expansion under construction
Forecast

Infrastructure

Electric GridPlanned Or Represented

1,000 MW

Meta states the New Albany facility will have at least 1 GW of capacity once construction is complete.

Site FacilityPlanned Or Represented

Large multi-building AI-optimized campus with continuing power, cooling and network expansion.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
Meta campus | New Albany | Central Ohio
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
1,000 MW
Design
Capacity Basis
Meta states the New Albany facility will have at least 1 GW of capacity once construction is complete.
Actual
Development Scale
Meta identifies New Albany as one of its facilities expected to reach at least 1 GW after construction
Actual
Development Milestone
The campus originally broke ground in 2017.
Actual
Material Uncertainty
The 1 GW value is a completed build target, not current operating capacity.
Actual
Boundary Context
Meta campus | New Albany | Central Ohio