Cartis diligence evidence schedule
Meta New Albany Prometheus AI Data Center Campus
PRJ-0743 · Site · New Albany, Ohio, United States
Record last updated Oct 28, 2026
Scope and capacity
In its October 19, 2026 New Albany update, Meta said Prometheus had trained frontier AI models. This establishes use of the cluster, not delivery or operation of the full planned 1 GW campus capacity. Meta is expanding its New Albany campus into a gigawatt-scale AI facility associated with the Prometheus supercluster. The disclosed 1 GW figure is the capacity expected once construction is complete. Meta is publicly identified in the project record for New Albany, Licking County area, OH, US. The disclosed development record includes meta identifies New Albany as one of its facilities expected to reach at least 1 GW after construction; the campus originally broke ground in 2017. Power and infrastructure include large multi-building AI-optimized campus with continuing power, cooling and network expansion. Meta states the New Albany facility will have at least 1 GW of capacity once construction is complete.
Headline: 1,000 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (8)
Location context · Meta campus | New Albany | Central Ohio
Actual · Meta New Albany Prometheus AI Data Center Campus (Project)
Claim 59494 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Meta infrastructure explained — New Albany capacity
Meta · Document date: Apr 1, 2026 · Primary
Source reference: SRC-3263 · Fact sheet · Recorded authority: Official primary
Source URL
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
Lifecycle status · Construction
Actual · Meta New Albany Prometheus AI Data Center Campus (Project)
Claim 59495 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Meta infrastructure explained — New Albany capacity
Meta · Document date: Apr 1, 2026 · Primary
Source reference: SRC-3263 · Fact sheet · Recorded authority: Official primary
Source URL
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
Reported capacity · 1,000 MW
Planned / design or future potential · Meta New Albany Prometheus AI Data Center Campus (Project)
Claim 59496 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Meta infrastructure explained — New Albany capacity
Meta · Document date: Apr 1, 2026 · Primary
Source reference: SRC-3263 · Fact sheet · Recorded authority: Official primary
Source URL
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
Capacity basis · Meta states the New Albany facility will have at least 1 GW of capacity once construction is complete.
Actual · Meta New Albany Prometheus AI Data Center Campus (Project)
Claim 59497 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Meta infrastructure explained — New Albany capacity
Meta · Document date: Apr 1, 2026 · Primary
Source reference: SRC-3263 · Fact sheet · Recorded authority: Official primary
Source URL
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
Development scale · Meta identifies New Albany as one of its facilities expected to reach at least 1 GW after construction
Actual · Meta New Albany Prometheus AI Data Center Campus (Project)
Claim 107712 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Meta infrastructure explained — New Albany capacity
Meta · Document date: Apr 1, 2026 · Primary
Source reference: SRC-3263 · Fact sheet · Recorded authority: Official primary
Source URL
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
- Statement regarding Meta nuclear energy projects
City of New Albany · Document date: Jan 15, 2026 · Corroborating
Source reference: SRC-6040 · Government record · Recorded authority: Official primary
Source URL
https://newalbanyohio.org/news/2026/01/statement-regarding-metas-nuclear-energy-projects/
https://newalbanyohio.org/news/2026/01/statement-regarding-metas-nuclear-energy-projects/
Development milestone · The campus originally broke ground in 2017.
Actual · Meta New Albany Prometheus AI Data Center Campus (Project)
Claim 107713 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Meta infrastructure explained — New Albany capacity
Meta · Document date: Apr 1, 2026 · Primary
Source reference: SRC-3263 · Fact sheet · Recorded authority: Official primary
Source URL
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
- Statement regarding Meta nuclear energy projects
City of New Albany · Document date: Jan 15, 2026 · Corroborating
Source reference: SRC-6040 · Government record · Recorded authority: Official primary
Source URL
https://newalbanyohio.org/news/2026/01/statement-regarding-metas-nuclear-energy-projects/
https://newalbanyohio.org/news/2026/01/statement-regarding-metas-nuclear-energy-projects/
Material uncertainty · The 1 GW value is a completed build target, not current operating capacity.
Actual · Meta New Albany Prometheus AI Data Center Campus (Project)
Claim 107714 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Meta infrastructure explained — New Albany capacity
Meta · Document date: Apr 1, 2026 · Primary
Source reference: SRC-3263 · Fact sheet · Recorded authority: Official primary
Source URL
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
- Statement regarding Meta nuclear energy projects
City of New Albany · Document date: Jan 15, 2026 · Corroborating
Source reference: SRC-6040 · Government record · Recorded authority: Official primary
Source URL
https://newalbanyohio.org/news/2026/01/statement-regarding-metas-nuclear-energy-projects/
https://newalbanyohio.org/news/2026/01/statement-regarding-metas-nuclear-energy-projects/
Boundary context · Meta campus | New Albany | Central Ohio
Actual · Meta New Albany Prometheus AI Data Center Campus (Project)
Claim 107715 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Meta infrastructure explained — New Albany capacity
Meta · Document date: Apr 1, 2026 · Primary
Source reference: SRC-3263 · Fact sheet · Recorded authority: Official primary
Source URL
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
https://about.fb.com/news/2026/04/infrastructure-explained-meta-data-centers/amp/
- Statement regarding Meta nuclear energy projects
City of New Albany · Document date: Jan 15, 2026 · Corroborating
Source reference: SRC-6040 · Government record · Recorded authority: Official primary
Source URL
https://newalbanyohio.org/news/2026/01/statement-regarding-metas-nuclear-energy-projects/
https://newalbanyohio.org/news/2026/01/statement-regarding-metas-nuclear-energy-projects/
Counterparties and capital
Meta Platforms, Inc. · Developer · CMP-0083
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.