New Albany, Ohio, United StatesPartially operational
Evidence
Planned / design
60 MW
Updated
Oct 28, 2026

STACK operates and expands its NAL01 campus in New Albany, Ohio. The current plan provides 60 MW of critical capacity, including 48 MW of new capacity backed by secured utility power. STACK Infrastructure is publicly identified in the project record for New Albany, Franklin County area, OH, US. The disclosed development record includes 60 MW total critical capacity; 48 MW of new secured-power capacity; two buildings; approximately 40-acre campus. Power and infrastructure include carrier-connected central Ohio campus designed for wholesale and hyperscale deployments. STACK currently identifies NAL01 as 60 MW of critical capacity, including 48 MW of new capacity with secured utility power.

Capacity

Reported capacity

Planned / design or future potential

60 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating and expansion programPartially operational

Project-wide phase for STACK New Albany Data Center Campus; capacity remains classified as design.

Milestones (2)
STACK New Albany project status and capacity disclosed

Jan 5, 2022 · Recorded actual event

Completed · Announced

Source not linked
Operational campus with immediate and build-to-suit expansion

Date not disclosed · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

STACK Infrastructure

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

STACK campus | New Albany | Central Ohio

Source

Development scale

Actual

60 MW total critical capacity

Source

Development milestone

Actual

48 MW of new secured power capacity

Source

Site configuration

Actual

Approximately 40-acre campus.

Source

Technical specifications

Power arrangement

Actual

Two buildings

Source

Additional project facts

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

STACK currently identifies NAL01 as 60 MW of critical capacity, including 48 MW of new capacity with secured utility power.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Partially operational

60 MW

STACK currently identifies NAL01 as 60 MW of critical capacity, including 48 MW of new capacity with secured utility power.

Site facility

Partially operational

Carrier-connected central Ohio campus designed for wholesale and hyperscale deployments.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (3)
AWS New Albany Data Center Campus

Operating · New Albany, Ohio, United States

Same locality: New Albany

Compare in a collection
Meta New Albany Prometheus AI Data Center Campus

Under construction · New Albany, Ohio, United States

Same locality: New Albany

Compare in a collection
Vantage OH1 New Albany Data Center Campus

Partially operational · New Albany, Ohio, United States

Same locality: New Albany

Compare in a collection