CyrusOne MIL2 Milan Data Center Campus

Milan, Lombardy, ItalyUnder construction
Capacity
54 MW
Planned critical IT
Lead participant
CyrusOne
Developer
Last updated
Aug 28, 2026
Most recent public record update

About CyrusOne MIL2 Milan Data Center Campus

CyrusOne MIL2 Milan Data Center Campus, also known as CyrusOne MIL2, is a data center project in Milan, Lombardy, IT associated with CyrusOne. 19.68-acre site; one three-story building; six 9 MW data halls; 18,000 square metres; 54 MW IT capacity. East Milan campus with grid and substation work, closed-loop cooling, heat-reuse readiness and renewable-energy design. 54 MW is the operator-published future facility or full-build design boundary.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load54 MWDesign · CyrusOne MIL2 Milan Data Center Campus
Future Potential54 MWDesign · CyrusOne MIL2 Milan Data Center Campus

Development

1 phases · 1 milestones
Development, permitting and phased deliveryUnder Construction

54 MW is the operator-published future facility or full-build design boundary. It is not operating IT load.

Aug 27, 2026
Current source record reviewed for CyrusOne MIL2
Completed

Infrastructure

Electric GridPlanned Or Represented

East Milan campus with grid and substation work, closed-loop cooling, heat-reuse readiness and renewable-energy design.

Cooling SystemPlanned Or Represented

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

13 facts
Location Context
CyrusOne MIL2 | Milan | Lombardy | IT
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
54 MW
Design
Capacity Basis
CyrusOne publishes 54 MW of critical IT capacity for this record boundary.
Actual
Location Context
CyrusOne MIL2 | Milan | Lombardy | IT
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
54 MW
Design
Capacity Basis
54 MW is the operator published future facility or full build design boundary.
Actual
Project Boundary
CyrusOne MIL2
Actual
Location Context
Milan, Lombardy, IT
Actual
Lifecycle Status
Construction
Actual
Development Detail
19.68-Acre site; one three story building; six 9 MW data halls; 18,000 square metres; 54 MW IT capacity.
Actual
Capacity Basis
54 MW is the operator published future facility or full build design boundary.
Actual