SK–AWS Ulsan AI Data Center

Ulsan, 31, South KoreaUnder construction
Capacity
1,000 MW
Planned / design
Lead participant
SK Group
Developer
Last updated
Aug 25, 2026
Most recent public record update

About SK–AWS Ulsan AI Data Center

Construction began August 29, 2025. The first 41 MW is targeted for November 2027 and the 103 MW facility for February 2029. A future 1 GW expansion remains a vision rather than an approved phase. Participants include SK Group as developer, SK Telecom as developer, SK Broadband as operator, SK Ecoplant as contractor. Published specifications include 41 MW planned capacity, 103 MW planned capacity, 1000 MW future potential. Development comprises Initial 41 MW stage (under construction), Expansion to 103 MW (planned). Key milestones include Initial 41 MW stage targeted to begin operations. (2027-11) and Cumulative 103 MW facility targeted for completion. (2029-02). lng supply: SK Gas LNG is expected to feed the site power chain. on site or adjacent power supply: SK Multi Utility is expected to produce energy for the site; contract and capacity are not public.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential41 MWActual · SK–AWS Ulsan AI Data Center
Future Potential103 MWActual · SK–AWS Ulsan AI Data Center
Future Potential1,000 MWActual · SK–AWS Ulsan AI Data Center

Development

2 phases · 4 milestones
Initial 41 MW stageUnder Construction

First operating stage; source does not establish whether 41 MW is IT load or total facility power.

Expansion to 103 MWPlanned

The 103-MW figure is cumulative design capacity for the expanded campus.

Jun 20, 2025
SK–AWS Ulsan investment announced
Completed
Aug 29, 2025
Physical campus broke ground
Completed
Nov 1, 2027
Initial 41 MW stage targeted to begin operations
Forecast
Feb 1, 2029
Cumulative 103 MW facility targeted for completion
Forecast

Infrastructure

Utility ServicePlanned Or Represented

SK Gas LNG is expected to feed the site power chain.

Electric GridPlanned Or Represented

SK Multi Utility is expected to produce energy for the site; contract and capacity are not public.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 2

Facts & sources

Published claims and their source links.

11 facts
Project Status
Under construction
Actual
Groundbreaking Date
2025-08-29
Actual
Initial Stage Capacity
41 MW
Actual
Planned Cumulative Capacity
103 MW
Actual
Initial Operations Target
2027-11
Actual
Planned Completion Target
2029-02
Actual
Future Potential Capacity
1,000 MW
Actual
Reported Joint Investment
7 KRW trillion
Actual
Reported Aws Investment Component
$4 billion
Actual
Reported Gpu Capacity
60,000 GPUs
Actual
Cooling Design
Hybrid air and liquid cooling
Actual