SK AI Infrastructure Superhighway
South KoreaStatus under reviewProgram
- Headline capacity
- See constituent sites
- Updated
- Oct 28, 2026
Construction began August 29, 2025. The first 41 MW is targeted for November 2027 and the 103 MW facility for February 2029. A future 1 GW expansion remains a vision rather than an approved phase.
Constituent sites / phases
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
No development records published.
Participants
SK Telecom
Operator
Sources by role
Operator (1)
- SK Telecom pursues 15GW AI data center buildout · Jul 5, 2026 · Corroborating
Operator (1)
- SK Group and AWS team up to build cloud infrastructure · Jun 22, 2025 · Primary
Additional project facts
Public-source research. Plans may change. See Evidence for sources and qualifications.