Vantage JHB1 Johor Data Center Campus

Sedenak, Johor, MalaysiaPartially operational
Capacity
300 MW
Planned critical IT
Lead participant
Vantage Data Centers
Developer
Last updated
Aug 28, 2026
Most recent public record update

About Vantage JHB1 Johor Data Center Campus

Vantage JHB1 Johor Data Center Campus, also known as Vantage JHB1 Johor, is a data center project in Sedenak, Johor, MY associated with Vantage Data Centers. 73-acre Sedenak Tech Park campus; three data centers; more than 930,000 square feet; 300 MW critical IT load at full build. Dual 275 kV feeds, diverse 33 kV building feeds, liquid-cooling readiness and multiple diverse fiber pathways. More than 300 MW is the planned three-building full-campus IT envelope after Vantage’s acquisition of the former Yondr development; it is not current operating capacity.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load300 MWDesign · Vantage JHB1 Johor Data Center Campus
Future Potential300 MWDesign · Vantage JHB1 Johor Data Center Campus

Development

1 phases · 1 milestones
Operating facility and documented expansionPartially Operational

More than 300 MW is the planned three-building full-campus IT envelope after Vantage’s acquisition of the former Yondr development; it is not current operating capacity.

Nov 23, 2025
Vantage completed JHB1 acquisition and APAC equity investment
Completed

Infrastructure

Electric GridEnergized

Dual 275 kV feeds, diverse 33 kV building feeds, liquid-cooling readiness and multiple diverse fiber pathways.

Cooling SystemOperational

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

Electric GridPlanned Or Represented

275 kV

Dual high-voltage feeds support the phased 300+ MW full-build plan.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 2Cooling & water: 1

Facts & sources

Published claims and their source links.

13 facts
Location Context
Vantage JHB1 Johor | Sedenak | Johor | MY
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
300 MW
Design
Capacity Basis
Vantage Data Centers publishes 300 MW of critical IT capacity for this record boundary.
Actual
Location Context
Vantage JHB1 Johor | Sedenak | Johor | MY
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
300 MW
Design
Capacity Basis
More than 300 MW is the planned three building full campus IT envelope after Vantage’s acquisition of the former Yondr development; it is not current operating capacity.
Actual
Site Area
73 acres
Actual
Building Count
3 data centers
Design
Full Build It Capacity
300+ MW
Forecast
Platform Equity Investment
$1,600,000,000
Transaction Scope
Prior Financing
Green loan
Actual