Stargate UAE

UAE–U.S. AI Campus, Abu Dhabi, United Arab EmiratesUnder construction
Evidence
Planned / design
1,000 MW
Updated
Oct 28, 2026

Stargate UAE is a planned 1 GW AI-compute cluster in Abu Dhabi, distinct from the announced 5 GW UAE–U.S. AI Campus that hosts it. G42 and Khazna are delivering the physical infrastructure for the OpenAI–Oracle operating partnership. The initial 200 MW facility remains the focus of published construction reporting. G42’s October 2025 update forecast delivery in 2026; ALEC’s August 2026 project table separately reported 52% contractor completion as of June and an expected contract-completion year of 2027. These are different milestones, not evidence of a confirmed operator go-live revision. ALEC describes a 200 MW electrical design, 200 MW of heat rejection and liquid/immersion cooling approaches. These design figures do not establish commissioned IT load. Its reported AED 5.2 billion first-phase contract is not the cost or financing of the full cluster. TAQA is developing a broader Stargate electricity and water scheme, but its capacity cannot be allocated to this cluster from the published report. Cisco’s announced role covers connectivity and security; installed carrier routes and resilience ratings remain undisclosed. Entity-level US advanced-computing authorizations progressed in July 2026, without proving chip delivery or local permit completion. Precise cluster parcels, project-specific financing, actual water demand and verified commissioning remain unresolved in the reviewed public evidence.

The planned 1 GW Stargate cluster is within the 5 GW host-campus envelope. The host envelope and cluster capacity overlap and are not additive. Related record

Capacity

Planned Stargate cluster capacity

Planned / design or future potential

1,000 MW

Source

Initial phase capacity

Planned / design or future potential

200 MW

Source

Host campus capacity

Planned / design or future potential

5,000 MW

Separate or overlapping physical boundary

Source

ALEC initial 200 MW contract progress as of June 2026

Contractor completion percentage; not commissioned IT

52 percent

Source

ALEC initial 200 MW contract expected completion, not operator go live

Contractor forecast reported in August 2026; not a confirmed operator revision

2027

Source

Initial 200 MW facility electrical design capacity, not operating IT

Planned / design or future potential

200 MW electrical

Source

Initial facility thermal heat rejection design, not electrical or IT load

Planned / design or future potential

200 MW thermal

Source

Initial 200 MW facility built up design area, not land area

Planned / design or future potential

250,000 square metres

Source

Initial 200 MW facility cooling design

Planned / design or future potential

ALEC describes liquid and immersion cooling approaches; commissioned configuration and operational deployment unverified system

Source

Broader TAQA Stargate utility service design demand; cluster allocation unknown

Broader utility scheme in development; not cluster load or proof of energization

2,000 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Initial 200 MW clusterUnder construction
Expansion to 1 GWPlanned
Broader 5 GW UAE–U.S. AI CampusRelated host campus

Participants

Khazna Data Centers

Physical developer

OpenAI

Operator and compute platform

Oracle

Operator and cloud infrastructure

TAQA Transmission

Broader Stargate utility scheme developer; cluster allocation unverified

Other participants (7)
G42

Project sponsor

NVIDIA

Accelerator supplier

Cisco

Network and security supplier

SoftBank Group

Strategic partner

ALEC Holdings / ALEC Construction

Initial 200 MW construction contractor

ALEMCO

Initial phase MEP and cooling

LINQ

Initial phase modular prefabrication

Capital & incentives

Capital claims

ALEC initial 200 MW contract remaining backlog as of June 2026

Contractor backlog; not project debt or total cluster cost

2,882 AED million

Source

ALEC initial 200 MW construction contract value

Contract value; not full cluster capex or project financing

5.2 AED billion

Source

Site & development

Host campus area

Reported

10 square miles

Source

Construction status

Company reported

Well underway status

Source

Initial 200 MW facility construction participants for client Khazna

Structural, design/modular, MEP, prefabrication and ELV roles

ALEC Construction: structure; ALEC Data Center Solutions: design/modular delivery; ALEMCO: MEP and cooling; LINQ: prefabrication; ALEC Technologies: ELV systems organizations

Source

Technical specifications

Power sources

Planned host campus

Nuclear solar and natural gas mix

Source

Broader TAQA Stargate utility water scheme

In development

47 MIGD pumping station, two water tanks and 40 km pipeline in development; infrastructure ratings are not consumption or an allocation to the 1 GW cluster or initial 200 MW phase scheme

Source

Additional project facts

Initial 200 MW developer delivery forecast

G42 October 2025 forecast; distinct from ALEC contract completion

2026

Source

Accelerator platform

Planned

NVIDIA Grace Blackwell GB300 system

Source

Geographic service radius

Company estimate

2,000 miles

Source

Broader TAQA Stargate utility transmission scheme

In development

14 Substations and over 400 km of cables/overhead lines in development; not confirmed completed cluster assets, and cluster allocation is unknown scheme

Source

Khazna corporate platform ownership, not project company equity

Platform level transaction

G42 majority; MGX and Silver Lake minority; e& exited. Stargate project-SPV equity and fee ownership are not established by this corporate transaction. ownership

Source

G42/Core42 entity level advanced computing regulatory context

Entity level export control rule

Authorized recipients under specified BIS conditions effective July 10, 2026; not proof of Stargate chip delivery, local permits or commissioning authorization

Source

G42/Core42 recipient authorization expiry absent subsequent BIS notice

Conditional entity level export authorization expiry; not a construction milestone

Apr 6, 2027

Source

Infrastructure & permits

Technical details (4)
Initial 200 MW facility cooling design

Contractor description

ALEC describes liquid and immersion cooling approaches; commissioned configuration and operational deployment unverified

Broader TAQA Stargate utility service design demand; cluster allocation unknown

Broader utility scheme in development; not cluster load or proof of energization

2 GW

Broader TAQA Stargate utility transmission scheme

In development

14 substations and over 400 km of cables/overhead lines in development; not confirmed completed cluster assets, and cluster allocation is unknown

Broader TAQA Stargate utility water scheme

In development

47 MIGD pumping station, two water tanks and 40 km pipeline in development; infrastructure ratings are not consumption or an allocation to the 1 GW cluster or initial 200 MW phase

G42/Core42 entity level advanced computing regulatory context · Authorized recipients under specified BIS conditions effective July 10, 2026; not proof of Stargate chip delivery, local permits or commissioning

Stargate UAE

Jul 14, 2026

Public-source research. Plans may change. See Evidence for sources and qualifications.