Cartis diligence evidence schedule
Stargate Doña Ana County Campus
PRJ-0619 · Site · Doña Ana County, New Mexico, United States
Record last updated Oct 28, 2026
Scope and capacity
Doña Ana County’s current Project Jupiter information forecasts initial operations in the fourth quarter of 2026 and Phase 1, including its microgrid, in the third quarter of 2028. These county forecasts do not confirm an achieved opening. The Stargate development in Doña Ana County, New Mexico is proceeding through county financing and environmental approvals under the Project Jupiter framework. The campus plan includes Oracle and related project entities, while a revised power plan proposes large-scale on-site fuel-cell generation. Those generation figures are separate from operating IT capacity, which has not been publicly disclosed.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (19)
Location context · Stargate site | Doña Ana County | New Mexico | United States
Actual · Stargate Doña Ana County Campus (Project)
Claim 54785 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI · Document date: Sep 23, 2025 · Primary
Source reference: SRC-2965 · Company announcement · Recorded authority: Party primary
Source URL
https://openai.com/index/five-new-stargate-sites/
https://openai.com/index/five-new-stargate-sites/
Lifecycle status · Preconstruction
Actual · Stargate Doña Ana County Campus (Project)
Claim 54786 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI · Document date: Sep 23, 2025 · Primary
Source reference: SRC-2965 · Company announcement · Recorded authority: Party primary
Source URL
https://openai.com/index/five-new-stargate-sites/
https://openai.com/index/five-new-stargate-sites/
Project identity · Stargate Doña Ana County Campus
Actual · Stargate Doña Ana County Campus (Project)
Claim 119708 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI · Document date: Sep 23, 2025 · Primary
Source reference: SRC-2965 · Company announcement · Recorded authority: Party primary
Source URL
https://openai.com/index/five-new-stargate-sites/
https://openai.com/index/five-new-stargate-sites/
- Executed industrial revenue bond documents for Project Jupiter
Doña Ana County, New Mexico · Document date: Jan 1, 2025 · Corroborating
Source reference: SRC-6556 · Government record · Recorded authority: Official primary
Source URL
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
Lifecycle status · Development program
Actual · Stargate Doña Ana County Campus (Project)
Claim 119709 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI · Document date: Sep 23, 2025 · Primary
Source reference: SRC-2965 · Company announcement · Recorded authority: Party primary
Source URL
https://openai.com/index/five-new-stargate-sites/
https://openai.com/index/five-new-stargate-sites/
- Executed industrial revenue bond documents for Project Jupiter
Doña Ana County, New Mexico · Document date: Jan 1, 2025 · Corroborating
Source reference: SRC-6556 · Government record · Recorded authority: Official primary
Source URL
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
Location · Doña Ana County, Doña Ana County, NM, US
Actual · Stargate Doña Ana County Campus (Project)
Claim 119710 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI · Document date: Sep 23, 2025 · Primary
Source reference: SRC-2965 · Company announcement · Recorded authority: Party primary
Source URL
https://openai.com/index/five-new-stargate-sites/
https://openai.com/index/five-new-stargate-sites/
- Executed industrial revenue bond documents for Project Jupiter
Doña Ana County, New Mexico · Document date: Jan 1, 2025 · Corroborating
Source reference: SRC-6556 · Government record · Recorded authority: Official primary
Source URL
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
Participant roles · OpenAI, Oracle
Actual · Stargate Doña Ana County Campus (Project)
Claim 119711 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI · Document date: Sep 23, 2025 · Primary
Source reference: SRC-2965 · Company announcement · Recorded authority: Party primary
Source URL
https://openai.com/index/five-new-stargate-sites/
https://openai.com/index/five-new-stargate-sites/
- Executed industrial revenue bond documents for Project Jupiter
Doña Ana County, New Mexico · Document date: Jan 1, 2025 · Corroborating
Source reference: SRC-6556 · Government record · Recorded authority: Official primary
Source URL
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
Development scale · The Stargate development in Doña Ana County, New Mexico is proceeding through county financing and environmental approvals under the Project Jupiter framework. The campus plan includes Oracle and related project entities, while a revised power plan proposes large scale on site fuel cell generation
Actual · Stargate Doña Ana County Campus (Project)
Claim 119713 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI · Document date: Sep 23, 2025 · Primary
Source reference: SRC-2965 · Company announcement · Recorded authority: Party primary
Source URL
https://openai.com/index/five-new-stargate-sites/
https://openai.com/index/five-new-stargate-sites/
- Executed industrial revenue bond documents for Project Jupiter
Doña Ana County, New Mexico · Document date: Jan 1, 2025 · Corroborating
Source reference: SRC-6556 · Government record · Recorded authority: Official primary
Source URL
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
Infrastructure · Those generation figures are separate from operating IT capacity, which has not been publicly disclosed.
Actual · Stargate Doña Ana County Campus (Project)
Claim 119714 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI · Document date: Sep 23, 2025 · Primary
Source reference: SRC-2965 · Company announcement · Recorded authority: Party primary
Source URL
https://openai.com/index/five-new-stargate-sites/
https://openai.com/index/five-new-stargate-sites/
- Executed industrial revenue bond documents for Project Jupiter
Doña Ana County, New Mexico · Document date: Jan 1, 2025 · Corroborating
Source reference: SRC-6556 · Government record · Recorded authority: Official primary
Source URL
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/IRB%20Series%202025A%20-%20Executed%20%26%20Recorded.pdf?t=202606101848290
Minimum initial investment · $50,000,000,000
Committed minimum · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-011 · Recorded claim type: Committed minimum · Review: Approved · Claim date: Sep 19, 2025
- Project Jupiter
Doña Ana County · Document date: Jan 6, 2026 · Supports
Source reference: JUP-01 · Government primary
Source URL
https://www.donaana.gov/about_us/project_jupiter/index.php
https://www.donaana.gov/about_us/project_jupiter/index.php
- Doña Ana County approves historic IRB for $165 billion
Doña Ana County · Document date: Sep 19, 2025 · Supports
Source reference: JUP-02 · Government primary
Source URL
https://www.donaana.gov/news_detail_T7_R35.php
https://www.donaana.gov/news_detail_T7_R35.php
Maximum irb authority · $165,000,000,000
Authorized ceiling over 30 years · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-012 · Recorded claim type: Authorized ceiling over 30 years · Review: Approved · Claim date: Sep 19, 2025
- Doña Ana County approves historic IRB for $165 billion
Doña Ana County · Document date: Sep 19, 2025 · Supports
Source reference: JUP-02 · Government primary
Source URL
https://www.donaana.gov/news_detail_T7_R35.php
https://www.donaana.gov/news_detail_T7_R35.php
- Executed Project Jupiter community benefits agreement
Doña Ana County · Document date: Apr 1, 2026 · Supports
Source reference: JUP-04 · Government primary
Source URL
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Community%20Benefits%20Agreement%20%28CBA%29%20Executed.pdf?t=202606221848480
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Community%20Benefits%20Agreement%20%28CBA%29%20Executed.pdf?t=202606221848480
Construction jobs · 2,500 jobs
Forecast 2025 2028 · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-013 · Recorded claim type: Forecast 2025 2028 · Review: Approved · Claim date: Sep 19, 2025
- Project Jupiter
Doña Ana County · Document date: Jan 6, 2026 · Supports
Source reference: JUP-01 · Government primary
Source URL
https://www.donaana.gov/about_us/project_jupiter/index.php
https://www.donaana.gov/about_us/project_jupiter/index.php
Full time jobs · 750+ jobs
Binding commitment · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-014 · Recorded claim type: Binding commitment · Review: Approved · Claim date: Sep 19, 2025
- Doña Ana County approves historic IRB for $165 billion
Doña Ana County · Document date: Sep 19, 2025 · Supports
Source reference: JUP-02 · Government primary
Source URL
https://www.donaana.gov/news_detail_T7_R35.php
https://www.donaana.gov/news_detail_T7_R35.php
- Executed Project Jupiter memorandum of understanding
Doña Ana County · Document date: Sep 1, 2025 · Supports
Source reference: JUP-03 · Government primary
Source URL
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Executed%20Memorandum%20of%20Understanding%20%28MOU%29.pdf?t=202606101845210
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Executed%20Memorandum%20of%20Understanding%20%28MOU%29.pdf?t=202606101845210
Part time jobs · 50+ jobs
Binding commitment · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-015 · Recorded claim type: Binding commitment · Review: Approved · Claim date: Sep 19, 2025
- Doña Ana County approves historic IRB for $165 billion
Doña Ana County · Document date: Sep 19, 2025 · Supports
Source reference: JUP-02 · Government primary
Source URL
https://www.donaana.gov/news_detail_T7_R35.php
https://www.donaana.gov/news_detail_T7_R35.php
- Executed Project Jupiter memorandum of understanding
Doña Ana County · Document date: Sep 1, 2025 · Supports
Source reference: JUP-03 · Government primary
Source URL
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Executed%20Memorandum%20of%20Understanding%20%28MOU%29.pdf?t=202606101845210
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Executed%20Memorandum%20of%20Understanding%20%28MOU%29.pdf?t=202606101845210
Phase 1 area · 400 acres
Planned · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-016 · Recorded claim type: Planned · Review: Approved · Claim date: Jan 6, 2026
- Project Jupiter
Doña Ana County · Document date: Jan 6, 2026 · Supports
Source reference: JUP-01 · Government primary
Source URL
https://www.donaana.gov/about_us/project_jupiter/index.php
https://www.donaana.gov/about_us/project_jupiter/index.php
Initial operations · 2026-Q4 period
Forecast · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-017 · Recorded claim type: Forecast · Review: Approved · Claim date: Jan 6, 2026
- Project Jupiter
Doña Ana County · Document date: Jan 6, 2026 · Supports
Source reference: JUP-01 · Government primary
Source URL
https://www.donaana.gov/about_us/project_jupiter/index.php
https://www.donaana.gov/about_us/project_jupiter/index.php
Phase 1 completion · 2028-Q3 period
Forecast · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-018 · Recorded claim type: Forecast · Review: Approved · Claim date: Jan 6, 2026
- Project Jupiter
Doña Ana County · Document date: Jan 6, 2026 · Supports
Source reference: JUP-01 · Government primary
Source URL
https://www.donaana.gov/about_us/project_jupiter/index.php
https://www.donaana.gov/about_us/project_jupiter/index.php
Average operational water · 20,000 gallons/day
Full buildout commitment · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-019 · Recorded claim type: Full buildout commitment · Review: Approved · Claim date: Sep 1, 2025
- Executed Project Jupiter memorandum of understanding
Doña Ana County · Document date: Sep 1, 2025 · Supports
Source reference: JUP-03 · Government primary
Source URL
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Executed%20Memorandum%20of%20Understanding%20%28MOU%29.pdf?t=202606101845210
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Executed%20Memorandum%20of%20Understanding%20%28MOU%29.pdf?t=202606101845210
Peak operational water cap · 60,000 gallons/day
Full buildout cap · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-020 · Recorded claim type: Full buildout cap · Review: Approved · Claim date: Sep 1, 2025
- Executed Project Jupiter memorandum of understanding
Doña Ana County · Document date: Sep 1, 2025 · Supports
Source reference: JUP-03 · Government primary
Source URL
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Executed%20Memorandum%20of%20Understanding%20%28MOU%29.pdf?t=202606101845210
https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Executed%20Memorandum%20of%20Understanding%20%28MOU%29.pdf?t=202606101845210
Microgrid sources · Natural gas plus battery storage; renewables under exploration system
Planned · Project Jupiter / Stargate Doña Ana (Project)
Claim AST-B3-021 · Recorded claim type: Planned · Review: Approved · Claim date: Jan 6, 2026
- Project Jupiter
Doña Ana County · Document date: Jan 6, 2026 · Supports
Source reference: JUP-01 · Government primary
Source URL
https://www.donaana.gov/about_us/project_jupiter/index.php
https://www.donaana.gov/about_us/project_jupiter/index.php
Counterparties and capital
OpenAI · Tenant, Compute customer · CMP-0007
Oracle · Developer, Cloud operator · CMP-0006
STACK Infrastructure · Developer · CMP-0102
BorderPlex Digital Assets · Development partner
Doña Ana County · Host and incentive issuer
$50,000,000,000 · Sep 19, 2025
Counterparties not specified. Scope not specified.
Sources (2)
- Project Jupiter · Jan 6, 2026
- Doña Ana County approves historic IRB for $165 billion · Sep 19, 2025
Financing record legacy-financing-AST-B3-011; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.