Stargate Doña Ana County Campus

Doña Ana County, New Mexico, United StatesPreconstruction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Doña Ana County’s current Project Jupiter information forecasts initial operations in the fourth quarter of 2026 and Phase 1, including its microgrid, in the third quarter of 2028. These county forecasts do not confirm an achieved opening. The Stargate development in Doña Ana County, New Mexico is proceeding through county financing and environmental approvals under the Project Jupiter framework. The campus plan includes Oracle and related project entities, while a revised power plan proposes large-scale on-site fuel-cell generation. Those generation figures are separate from operating IT capacity, which has not been publicly disclosed.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development programAnnounced or preconstruction

Stargate Doña Ana County Campus: Development program.

Initial operationsUnder construction
Phase 1 and microgridPlanned
Long-term campus buildoutPlanned
Milestones (2)
Stargate Doña Ana County Campus — Development program

Sep 23, 2025 · Event timing type not established

In progress · Announced

Source not linked
The Stargate development in Doña Ana County, New Mexico is proceeding through county financing and environmental approvals under the Project Jupiter framework.

Date not disclosed · Event timing type not established

In progress · Status changed

Source not linked

Participants

OpenAI

Tenant · Compute customer

Sources by role
Oracle

Developer · Cloud operator

Sources by role
Other participants (2)
BorderPlex Digital Assets

Development partner

Doña Ana County

Host and incentive issuer

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Minimum initial investment

Committed minimum

$50,000,000,000

Project Jupiter / Stargate Doña Ana · Project

Source

Maximum irb authority

Authorized ceiling over 30 years

$165,000,000,000

Project Jupiter / Stargate Doña Ana · Project

Source

Financing records

Minimum initial investment

$50bn

Sep 19, 2025

Parties & sources

Legacy figure

Counterparties not specified. Scope not specified.

Sources (2)
Evidence record

Site & development

Location context

Actual

Stargate site | Doña Ana County | New Mexico | United States

Source

Location

Actual

Doña Ana County, Doña Ana County, NM, US

Source

Development scale

Actual

The Stargate development in Doña Ana County, New Mexico is proceeding through county financing and environmental approvals under the Project Jupiter framework. The campus plan includes Oracle and related project entities, while a revised power plan proposes large scale on site fuel cell generation

Source

Construction jobs

Forecast 2025 2028

2,500 jobs

Project Jupiter / Stargate Doña Ana · Project

Source

Phase 1 area

Planned

400 acres

Project Jupiter / Stargate Doña Ana · Project

Source

Phase 1 completion

Forecast

2028-Q3 period

Project Jupiter / Stargate Doña Ana · Project

Source

Technical specifications

Average operational water

Full buildout commitment

20,000 gallons/day

Project Jupiter / Stargate Doña Ana · Project

Source

Peak operational water cap

Full buildout cap

60,000 gallons/day

Project Jupiter / Stargate Doña Ana · Project

Source

Microgrid sources

Planned

Natural gas plus battery storage; renewables under exploration system

Project Jupiter / Stargate Doña Ana · Project

Source

Additional project facts

Lifecycle status

Actual

Preconstruction

Source

Project identity

Actual

Stargate Doña Ana County Campus

Source

Lifecycle status

Actual

Development program

Source

Participant roles

Actual

OpenAI, Oracle

Source

Infrastructure

Actual

Those generation figures are separate from operating IT capacity, which has not been publicly disclosed.

Source

Full time jobs

Binding commitment

750+ jobs

Project Jupiter / Stargate Doña Ana · Project

Source

Part time jobs

Binding commitment

50+ jobs

Project Jupiter / Stargate Doña Ana · Project

Source

Initial operations

Forecast

2026-Q4 period

Project Jupiter / Stargate Doña Ana · Project

Source

Infrastructure & permits

Technical details (4)
Electric grid

Planned or represented

Project power infrastructure.

Site facility

Planned or represented

Those generation figures are separate from operating IT capacity, which has not been publicly disclosed.

Average operational water

Full buildout commitment

20,000 gallons/day

Peak operational water cap

Full buildout cap

60,000 gallons/day

Air authorization · Under review

Stargate Doña Ana County Campus

New Mexico Environment Department

Jun 3, 2026

Sources (2)

Public-source research. Plans may change. See Evidence for sources and qualifications.