STACK ZUR02 Zurich Data Center Campus
- Planned critical IT
- 36 MW
- Updated
- Oct 28, 2026
STACK ZUR02 is a single-building Zurich-region facility at Beringen. Independent tracking records an operational stage change in November 2025, correcting the prior preconstruction label. The 36 MW figure remains a design boundary because tenant utilization and energized load are not public. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
STACK ZUR02 is a single-building Zurich-region facility at Beringen. Independent tracking records an operational stage change in November 2025, correcting the prior preconstruction label. The 36 MW figure remains a design boundary because tenant utilization and energized load are not public. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.
Milestones (2)
Nov 2025 · Recorded actual event
Completed · Commercial operation
Source not linkedAug 29, 2026 · Recorded actual event
Completed · Status changed
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- STACK Infrastructure STACK ZUR02 profile · Aug 28, 2026 · Primary
Site & development
Additional project facts
Capacity basis
ActualSTACK Infrastructure publishes 36 MW of critical IT capacity for this record boundary.
SourceCapacity basis
Actual36 MW is the published facility design boundary. Independent tracking reports operational status since November 2025, but live tenant utilization is not disclosed.
SourceCapacity basis
Actual36 MW is the published facility design boundary. Independent tracking reports operational status since November 2025, but live tenant utilization is not disclosed.
SourceInfrastructure & permits
Technical details (3)
Planned or represented
36 MW
36 MW is the published facility design boundary. Independent tracking reports operational status since November 2025, but live tenant utilization is not disclosed.
Planned or represented
Expansion-focused Swiss facility for cloud and other large deployments in a land- and power-constrained market.
Planned or represented
Cooling and resilience architecture is described at facility or campus level; instantaneous draw and tenant utilization remain undisclosed.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (2)
Partially operational · Zurich, Switzerland
Same locality: Zurich · Shared participant: STACK Infrastructure
Compare in a collectionPreconstruction · Zurich, Switzerland
Same locality: Zurich · Shared participant: STACK Infrastructure
Compare in a collection