Skip to content
All records
Data center siteSite record

Sabey SDC Quincy Data Center Campus

Quincy, Washington, United StatesOperating / Stabilized
Capacity
123 MW
Planned / design
Lead participant
Sabey Data Centers
Operator
Last updated
Sep 1, 2026
Most recent public record update

About Sabey SDC Quincy Data Center Campus

Sabey SDC Quincy is a five-building operating campus at 2200 M Street NE in Quincy, Washington. The 530,000-square-foot campus provides 123 MW of data center power and uses Grant County’s hydroelectric system, with more than ten Tier 1 network providers and a published design PUE of 1.2. SDC1, SDC2 and generic Sabey Quincy references are consolidated into this single canonical campus.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design123 MWActual · Sabey SDC Quincy Data Center Campus

Development

1 phases · 1 milestones
Buildings A–EOperational

Five operating data center buildings delivered in phases.

Mar 18, 2019
SEPA record issued for Building D
Completed

Infrastructure

Electric GridOperational

123 MW

Campus data center power served in Grant County PUD territory.

FiberOperational

More than ten Tier 1 network providers connect the campus.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

4 facts
Reported Capacity
123 MW operating campus design capacity MW
Actual
Building Count
5
Actual
Building Area
530,000 sq. ft.
Actual
Design Pue
1.2 ratio
Actual