QLevr Inver Grove Heights Data Center
- Planned / design
- 5 MW
- Updated
- Oct 28, 2026
- Utility
- Xcel Energy
The City of Inver Grove Heights confirms a final moratorium-exemption reading on September 14, 2026 and major site-plan approval on September 28. The development contract and building permit remain separate requirements; this is not confirmation of construction or operation. QLevr proposes a roughly 55,000-square-foot data center on an approximately 14-acre industrial parcel at 5890 Carmen Avenue in Inver Grove Heights. The city found the project exempt from an environmental assessment worksheet in July 2026, while the major site plan was then unresolved amid a data center moratorium, a proposed project-specific removal and threatened developer litigation; the September city decisions provide the later approval history.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Current proposal-review phase; no construction or operating phase is created.
1 building
Initial power configuration within the same proposed building.
1 building
Full-build proposal only.
Milestones (9)
Mar 26, 2026 · Recorded actual event
Completed · Status changed
Source not linkedApr 7, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedApr 27, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedMay 11, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedJun 26, 2026 · Recorded actual event
Completed · Cancelled
Source not linkedJul 21, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedJul 27, 2026 · Recorded actual event
Completed · Permit approved
Source not linkedAug 10, 2026 · Event timing type not established
In progress · Cancelled
Source not linkedAug 24, 2026 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Data Center Project Updates · Aug 10, 2026 · Primary
Developer (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Corroborating
Other participants (7)
Contractor
Sources by role
Contractor (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Primary
Government authority
Sources by role
Government authority (1)
- Data Center Project Updates · Aug 10, 2026 · Primary
Government authority (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Corroborating
Government authority (1)
- Third Reading of Interim Ordinance Authorizing Study of Data Centers · Jun 26, 2026 · Corroborating
Government authority
Sources by role
Government authority (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Primary
Government authority
Sources by role
Government authority (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Primary
Government authority
Sources by role
Government authority (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Primary
Government authority
Sources by role
Government authority (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Primary
Utility provider
Sources by role
Utility provider (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Primary
Site & development
Technical specifications
Additional project facts
Data center moratorium status
PermittedApproved for one year; project specific removal ordinance received first reading
SourceInfrastructure & permits
Technical details (9)
Reported context
3 MW initial
Initial proposed electric demand; consultant report relies partly on applicant records.
Planned or represented
5 MW ultimate
Ultimate proposed electric demand; not operating load.
Potential or planned
6 closed loop air cooled chillers
Closed-loop system with one-time fill and limited makeup-water model.
Planned or represented
60,000 gallons
Initial closed-loop fill; not annual consumption.
Planned or represented
70,000 gallons
Full-build closed-loop fill; not annual consumption.
Reported context
196 gallons/day
Model output, not measured use.
Reported context
332 gallons/day
Model output, not measured use.
Potential or planned
23 feet wall height
Acoustic wall proposed with modeled 40 dBA/54 dBC maximum receptor noise.
Potential or planned
Emergency diesel generators are described, but exact count and permit path remain unresolved.
Project map
Other · Under review
QLevr Carmen Avenue proposal
City of Inver Grove Heights
Jun 26, 2026
Sources (1)
- Data Center Project Updates · Aug 10, 2026 · Primary
Other · Under review
QLevr Carmen Avenue proposal
Federal Aviation Administration
Jul 21, 2026
Sources (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Primary
Other · Denied
QLevr Carmen Avenue proposal
City of Inver Grove Heights
Jul 27, 2026
Sources (2)
- Data Center Project Updates · Aug 10, 2026 · Primary
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Corroborating
Other · Issued
QLevr Carmen Avenue proposal
City of Inver Grove Heights
Aug 10, 2026
Sources (2)
- Data Center Project Updates · Aug 10, 2026 · Primary
- Third Reading of Interim Ordinance Authorizing Study of Data Centers · Jun 26, 2026 · Corroborating
Air authorization · Documented
QLevr Carmen Avenue proposal
Minnesota Pollution Control Agency
Sources (1)
- Third-Party Consultant Report on Review of the EAW Petition · Jul 21, 2026 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (3)
Preconstruction · Pine Island, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collectionUnder construction · Rosemount / UMore Park, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collectionProposed · Monticello Orderly Annexation Area, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collection