Monticello Tech Technology Campus
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
- Utility
- Xcel Energy
Monticello Tech proposes an approximately 547–550-acre technology campus with two to three million square feet of gross floor area. A second application package arrived August 3, 2026 and the city is still deciding whether it is complete.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Rezone, DCPUD CUP and preliminary plat await a completeness determination.
Applicant planning assumption only; exact footprints and tenant requirements await a future site plan. Source wording: 5–10 buildings. Canonical building count is blank because this is a planning range, not an exact count.
Milestones (9)
Dec 3, 2024 · Recorded actual event
Completed · Permit filed
Source not linkedFeb 24, 2025 · Recorded actual event
Completed · Status changed
Source not linkedJan 26, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedApr 27, 2026 · Recorded actual event
Completed · Permit approved
Source not linkedJul 6, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedJul 20, 2026 · Recorded actual event
Completed · Status changed
Source not linkedAug 3, 2026 · Recorded actual event
Completed · Permit filed
Source not linkedQ1 2028 · Forecast / planned record
Forecast · Forecast completion
Source not linkedQ4 2030 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Monticello Tech DCPUD Permit Application Narrative V2 · Aug 3, 2026 · Corroborating
Developer (1)
- Monticello Tech · Primary
Other participants (3)
Government authority
Sources by role
Government authority (1)
- City of Monticello Ordinance 865 · Apr 27, 2026 · Corroborating
Government authority (1)
- Monticello Tech · Primary
Government authority (1)
- Data Centers · Corroborating
Contractor
Sources by role
Contractor (1)
- Monticello Tech DCPUD Permit Application Narrative V2 · Aug 3, 2026 · Primary
Utility provider
Sources by role
Utility provider (1)
- Monticello Tech DCPUD Permit Application Narrative V2 · Aug 3, 2026 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Investment commitment
Amount not disclosedAug 3, 2026
Applicant describes a $1B-plus development; no committed financing, lender or spend-to-date is verified. Source wording: more than USD 1 billion.
Parties & sources
Monticello Tech, LLC (Sponsor)
Sources (1)
- Monticello Tech DCPUD Permit Application Narrative V2 · Aug 3, 2026
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (5)
Potential or planned
345 kV
System Impact Study completed; service depends on developer-funded upgrades and a Facilities Study.
Potential or planned
New substation concept; final design, route and permit remain pending.
Planned or represented
75,000 gallons per day
Average domestic water demand under dry-cooling scenario; no process-water demand claimed.
Planned or represented
75,000 gallons per day
Applicant study assumption; not current use.
Planned or represented
Applicant says operational need would be below 25 MW; this is not IT load. Source wording: below 25 MW. Canonical capacity is blank because the current model has no upper-bound operator; this is not asserted as IT load.
Project map
Other · Issued
Monticello Industrial Final AUAR and Mitigation Plan
City of Monticello
Jan 26, 2026
Sources (1)
- Monticello Tech · Primary
Other · Issued
Data Center Planned Unit Development Ordinance 865
City of Monticello
Apr 27, 2026
Sources (2)
- City of Monticello Ordinance 865 · Apr 27, 2026 · Corroborating
- Data Centers · Primary
Other · Under review
DCPUD conditional use permit application
City of Monticello
Aug 3, 2026
Sources (2)
- Monticello Tech DCPUD Permit Application Narrative V2 · Aug 3, 2026 · Corroborating
- Monticello Tech · Primary
Other · Under review
Rezone application
City of Monticello
Aug 3, 2026
Sources (2)
- Monticello Tech DCPUD Permit Application Narrative V2 · Aug 3, 2026 · Corroborating
- Monticello Tech · Primary
Other · Under review
Preliminary plat application
City of Monticello
Aug 3, 2026
Sources (2)
- Monticello Tech DCPUD Permit Application Narrative V2 · Aug 3, 2026 · Corroborating
- Monticello Tech · Primary
Other · Applied
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (3)
Preconstruction · Pine Island, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collectionUnder construction · Rosemount / UMore Park, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collectionDelayed · 5890 Carmen Avenue, Inver Grove Heights, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collection