Google Pine Island Data Center
Preconstruction · Pine Island, Minnesota, United States
Monticello Tech proposes an approximately 547–550-acre technology campus with two to three million square feet of gross floor area. A second application package arrived August 3, 2026 and the city is still deciding whether it is complete.
Projects sharing a market, utility, or organization.
Preconstruction · Pine Island, Minnesota, United States
On hold / Delayed · 5890 Carmen Avenue, Inver Grove Heights, Minnesota, United States
Under construction · Rosemount / UMore Park, Minnesota, United States
No additional capacity claims are published.
Rezone, DCPUD CUP and preliminary plat await a completeness determination.
Applicant planning assumption only; exact footprints and tenant requirements await a future site plan. Source wording: 5–10 buildings. Canonical building count is blank because this is a planning range, not an exact count.
345 kV
System Impact Study completed; service depends on developer-funded upgrades and a Facilities Study.
New substation concept; final design, route and permit remain pending.
75,000 gallons per day
Average domestic water demand under dry-cooling scenario; no process-water demand claimed.
75,000 gallons per day
Applicant study assumption; not current use.
Applicant says operational need would be below 25 MW; this is not IT load. Source wording: below 25 MW. Canonical capacity is blank because the current model has no upper-bound operator; this is not asserted as IT load.
No map point available