Meta Rosemount Data Center
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
- Utility
- Xcel Energy
Meta is building an approximately 715,000-square-foot data center campus on 280 acres at UMore Park in Rosemount. Meta Rosemount Data Center is in Rosemount / UMore Park, MN, US and is a data center campus with construction status.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
2 buildings
Two primary data center buildings plus support structures.
Milestones (3)
Oct 12, 2023 · Recorded actual event
Completed · Permit approved
Source not linkedMar 14, 2024 · Recorded actual event
Completed · Announced
Source not linked2026 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Customer
Sources by role
Customer (1)
- PUC approves Meta-affiliate electric-service agreements · Oct 12, 2023 · Primary
Owner
Sources by role
Owner (1)
- Meta buys more Rosemount land for potential expansion · Feb 22, 2025 · Corroborating
Owner (1)
Developer
Sources by role
Developer (1)
- Hello Rosemount · Mar 14, 2024 · Primary
Developer (1)
- Meta Rosemount data-center announcement · Mar 14, 2024 · Corroborating
Other participants (3)
Utility provider
Sources by role
Utility provider (1)
- Xcel Energy to power new Meta data center · Mar 14, 2024 · Primary
Utility provider (1)
- PUC approves Meta-affiliate electric-service agreements · Oct 12, 2023 · Corroborating
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Commercial contract
$39,700,000Dec 31, 2023
Reported purchase price for approximately 280-acre main campus site.
Parties & sources
Jimnist, LLC (Other) · University of Minnesota (Other)
Sources (1)
- Meta keeps buying Rosemount land · Oct 15, 2025
Incentives
Sales tax exemption
for 35 years
Proposed · Dakota County
Minnesota program may apply, but reviewed sources did not establish project-specific certification or benefit amount.
Site & development
Additional project facts
Infrastructure & permits
Technical details (2)
Secured or contracted
Customer-funded dedicated upgrades; secondary source reports 10 MW initially and at least 75 MW over ten years.
Secured or contracted
Annual use matched through renewable energy and RECs; not a direct dedicated generation capacity claim.
Project map
Interconnection · Issued
Amber Kestral electric-service contracts
Minnesota Public Utilities Commission
Oct 12, 2023
Sources (1)
- PUC approves Meta-affiliate electric-service agreements · Oct 12, 2023 · Primary
Grading · Issued
Project Bigfoot development approvals
City of Rosemount
Dec 31, 2023
Sources (1)
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (3)
Preconstruction · Pine Island, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collectionProposed · Monticello Orderly Annexation Area, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collectionDelayed · 5890 Carmen Avenue, Inver Grove Heights, Minnesota, United States
Shared participant: Xcel Energy · Same market: Minnesota, United States
Compare in a collection