Meta Rosemount Data Center

Rosemount / UMore Park, Minnesota, United StatesUnder construction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026
Utility
Xcel Energy

Meta is building an approximately 715,000-square-foot data center campus on 280 acres at UMore Park in Rosemount. Meta Rosemount Data Center is in Rosemount / UMore Park, MN, US and is a data center campus with construction status.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Main campus constructionUnder construction

2 buildings

Two primary data center buildings plus support structures.

Milestones (3)
Minnesota PUC approves service agreements

Oct 12, 2023 · Recorded actual event

Completed · Permit approved

Source not linked
Meta announces Rosemount campus

Mar 14, 2024 · Recorded actual event

Completed · Announced

Source not linked
Operations target

2026 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Amber Kestral, LLC

Customer

Sources by role
Customer (1)
Jimnist, LLC

Owner

Sources by role
Meta Platforms, Inc.

Developer

Sources by role
Developer (1)
Developer (1)
Other participants (3)
City of Rosemount

Government authority

Sources by role
Government authority (1)
Mortenson

Contractor

Sources by role
Contractor (1)
Xcel Energy

Utility provider

Sources by role
Utility provider (1)
Utility provider (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Investment

Source report

$800,000,000 minimum

Source

Financing records

Commercial contract

$39,700,000

Dec 31, 2023

Reported purchase price for approximately 280-acre main campus site.

Parties & sources

Jimnist, LLC (Other) · University of Minnesota (Other)

Sources (1)

Incentives

Sales tax exemption

for 35 years

Proposed · Dakota County

Minnesota program may apply, but reviewed sources did not establish project-specific certification or benefit amount.

Site & development

Main site area

Actual

280 acres

Source

Floor area

Actual

715,000 sq. ft.

Source

Peak construction jobs

Source report

1,000+ jobs

Source

Additional project facts

Operations jobs

Source report

100 jobs approximate

Source

Operations target

Actual

2026

Source

Renewable matching

Actual

Annual electricity matched through renewable energy and RECs

Source

Infrastructure & permits

Technical details (2)
Electric grid

Secured or contracted

Customer-funded dedicated upgrades; secondary source reports 10 MW initially and at least 75 MW over ten years.

Renewable energy supply

Secured or contracted

Annual use matched through renewable energy and RECs; not a direct dedicated generation capacity claim.

Interconnection · Issued

Amber Kestral electric-service contracts

Minnesota Public Utilities Commission

Oct 12, 2023

Sources (1)
Grading · Issued

Project Bigfoot development approvals

City of Rosemount

Dec 31, 2023

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (3)
Google Pine Island Data Center

Preconstruction · Pine Island, Minnesota, United States

Shared participant: Xcel Energy · Same market: Minnesota, United States

Compare in a collection
Monticello Tech Technology Campus

Proposed · Monticello Orderly Annexation Area, Minnesota, United States

Shared participant: Xcel Energy · Same market: Minnesota, United States

Compare in a collection
QLevr Inver Grove Heights Data Center

Delayed · 5890 Carmen Avenue, Inver Grove Heights, Minnesota, United States

Shared participant: Xcel Energy · Same market: Minnesota, United States

Compare in a collection