Skip to content
All records
Data center siteSite record

Meta Rosemount Data Center

Rosemount / UMore Park, Minnesota, United StatesUnder construction
Capacity
No public figure
Lead participant
Meta Platforms, Inc.
Developer
Last updated
Aug 24, 2026
Most recent public record update

About Meta Rosemount Data Center

Meta is building an approximately 715,000-square-foot data center campus on 280 acres at UMore Park in Rosemount. Meta Rosemount Data Center is in Rosemount / UMore Park, MN, US and is a data center campus with construction status. Participants include Meta Platforms, Inc. as developer, Jimnist, LLC as owner, Amber Kestral, LLC as customer, Xcel Energy as utility provider. Development comprises Main campus construction (construction). Key milestones include Meta announces Rosemount campus. (2024-03-14) and Operations target. (2026-12-31). electric utility service: Customer-funded dedicated upgrades; secondary source reports 10 MW initially and at least 75 MW over ten years. renewable energy matching: Annual use matched through renewable energy and RECs; not a direct dedicated generation capacity claim. Permitting includes land use and site development for Project Bigfoot development approvals (approved and under construction) and utility contract approval for Amber Kestral electric-service contracts (approved). Capital records include land acquisition for Reported purchase price for approximately 280-acre main campus site. Incentives include qualified data center sales tax exemption (potential program project certification not publicly disclosed) for Minnesota program may apply, but reviewed sources did not establish project-specific certification or benefit amount.

Projects sharing a market, utility, or organization.

3 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

1 phases · 3 milestones
Main campus constructionUnder Construction

Two primary data center buildings plus support structures.

2 buildings

Oct 12, 2023
Minnesota PUC approves service agreements
Completed
Mar 14, 2024
Meta announces Rosemount campus
Completed
Dec 31, 2026
Operations target
Forecast

Infrastructure

Electric GridSecured Or Contracted

Customer-funded dedicated upgrades; secondary source reports 10 MW initially and at least 75 MW over ten years.

Renewable Energy SupplySecured Or Contracted

Annual use matched through renewable energy and RECs; not a direct dedicated generation capacity claim.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 2

Facts & sources

Published claims and their source links.

7 facts
Main Site Area
280 acres
Actual
Floor Area
715,000 sq. ft.
Actual
Investment
$800,000,000 minimum
Fact
Operations Jobs
100 jobs approximate
Fact
Peak Construction Jobs
1,000+ jobs
Fact
Operations Target
2026
Actual
Renewable Matching
Annual electricity matched through renewable energy and RECs
Actual