Pure DC AUH01 Yas Island Campus

Yas Island / Abu Dhabi, AZ, United Arab EmiratesPartially operational
Evidence
Planned / design
48 MW
Updated
Oct 28, 2026

Campus boundary for two buildings and shared 48 MW design; the 7 MW approval is an increment within 48 MW, not additional.

Constituent sites / phases

Capacity

Current full campus design capacity

Planned / design or future potential

48 MW

Source

Approved design optimization increment

Planned / design or future potential

7 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

7 MW design optimizationAnnounced or preconstruction

The 7 MW optimization increases the prior 41 MW design to 48 MW total.

Milestones (3)
Securitas selected as security partner

May 28, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked
Final TAQA approvals for 48 MW design announced

Apr 27, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
Pure DC announced USD2.7bn platform financing package

May 27, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked

Participants

Pure Data Centres Group

Operator

Sources by role
Operator (1)
Operator (1)

Capital & incentives

Financing records

Corporate financing facility

$550m

May 27, 2026

Pure DC corporate-level facility; may support growth across the platform but no AUH01 allocation is disclosed.

Parties & sources

ABN AMRO (Named financing institution) · Allianz Global Investors (Named financing institution) · Pure Data Centres Group (Borrower) · SMBC (Named financing institution)

Site & development

Site area

Source report

16.19 acres

Source

Physical building count

Source report

2 buildings

Source

Total building area

Source report

40,150 square meters

Source

Technical specifications

Water system

Actual

Closed loop

Source

Cooling design

Actual

Hybrid air and liquid cooling

Source

Additional project facts

Average annualized PUE

Source report

1.38 PUE

Source

Final utility approval received

Source report

True

Source

Electricity matched with irecs

Source report

100 percent of 2025 electricity

Source

Security provider

Actual

Securitas

Source

Infrastructure & permits

Technical details (3)
Electric grid

Partially operational

48 MW campus design

Final approvals include 7 MW design optimization within 48 MW total; current live load not disclosed.

Cooling system

Operational

Hybrid air and liquid cooling with a closed-loop water system.

Renewable energy supply

Operational

100 percent electricity matched

I-RECs match 2025 electricity use; no claim of physical on-site renewable generation.

Permit · Status not stated

AUH01 7 MW design optimization

TAQA Morocco

Apr 27, 2026

Sources (1)