Project Matador HyperGrid Power Site
- Utility capacity
- 86 MW
- Updated
- Oct 28, 2026
- Utility
- Southwestern Public Service Company
On October 15, 2026, Fermi reported that three GE Vernova 6B gas turbines had arrived at Project Matador, following its September 28 selection of NAES to operate the natural-gas fleet. Equipment arrival and operator selection do not establish energization or first power; gas-generation capacity is not data center IT capacity. Project Matador's HyperGrid is an actively financed and permitted private-power development with gas assets, grid supply and longer-term nuclear, solar and battery plans. Project Matador HyperGrid Power Site is located in Texas Panhandle near Amarillo, TX, US and is a generation site in construction status.
Capacity
Planned nuclear capacity
Planned / design or future potential4.4 GW
Generation capacity; not IT capacity
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Utility supply is distinct from onsite generation.
Approximately 2 GW secured/contracted assets; no operating capacity.
Air permit is not construction completion.
Would bring total gas authorization to about 11 GW if approved.
4 buildings
Long-term 4.4 GW plan; no operating unit.
Milestones (3)
Feb 25, 2026 · Recorded actual event
Completed · Event type not stated
Source not linkedMar 27, 2026 · Recorded actual event
Completed · Event type not stated
Source not linkedJul 21, 2026 · Recorded actual event
Completed · Event type not stated
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Fermi Form 10-Q for quarter ended March 31, 2026 · May 14, 2026 · Primary
Developer (1)
- Project Matador current project website · Corroborating
Other participants (3)
Contractor
Sources by role
Contractor (1)
- Fermi Form S-11 registration statement · Sep 15, 2025 · Primary
Supplier
Sources by role
Supplier (1)
- First Siemens Energy turbines arrive for Project Matador · Jul 21, 2026 · Corroborating
Supplier (1)
- Fermi MUFG equipment financing 8-K · Feb 10, 2026 · Primary
Utility provider
Sources by role
Utility provider (1)
- Fermi 2025 Form 10-K · Mar 30, 2026 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Equipment financing facility
$500mFeb 10, 2026
Up-to commitment for three Siemens F-class turbines and related equipment; not full project financing.
Parties & sources
Fermi Inc. (Sponsor and indirect borrower) · MUFG (Lender)
Sources (2)
- Fermi Form 10-Q for quarter ended March 31, 2026 · May 14, 2026
- Fermi MUFG equipment financing 8-K · Feb 10, 2026
High voltage equipment facility
$200mFeb 19, 2026
Facility arranged by Cape; more than USD 100 million initially committed by Keystone.
Parties & sources
Cape Commercial Finance (Arranger) · Fermi Inc. (Sponsor) · Keystone National Group (Lender)
Sources (1)
- Fermi Keystone/Cape equipment facility · Feb 19, 2026
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (6)
Secured or contracted
200 MW
86 MW expected and additional 114 MW targeted but not fully committed.
Under construction
2 GW
Approximately 2 GW secured/contracted assets; 780 MW of F-class turbines reached Houston.
Permitted or installed
6 GW
Air authorization, not installed or operating capacity.
Potential or planned
4.4 GW
Four-reactor long-term plan; licensing and financing incomplete.
Planned or represented
No site-specific installed MW disclosed.
Planned or represented
No site-specific installed MWh disclosed.
Project map
Permit · Status not stated
Project Matador nuclear program
U.S. Nuclear Regulatory Commission
Jun 17, 2025
Sources (1)
- Fermi Form S-11 registration statement · Sep 15, 2025 · Primary
Permit · Issued
Project Matador gas generation
Texas Commission on Environmental Quality
Feb 25, 2026
Sources (2)
- Fermi Form 10-Q for quarter ended March 31, 2026 · May 14, 2026 · Primary
- Fermi receives final clean-air permit approval · Feb 25, 2026 · Corroborating
Permit · Status not stated
Incremental gas generation
Texas Commission on Environmental Quality
Mar 27, 2026
Sources (2)
- Fermi Form 10-Q for quarter ended March 31, 2026 · May 14, 2026 · Primary
- Fermi 2025 Form 10-K · Mar 30, 2026 · Corroborating
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (1)
Preconstruction · Texas Panhandle near Amarillo, Texas, United States
Same locality: Texas Panhandle near Amarillo · Shared participant: Fermi Inc.
Compare in a collection