Skip to content
All records
Data center siteSite record

Project Matador HyperGrid Power Site

Texas Panhandle near Amarillo, Texas, United StatesUnder construction
Capacity
86 MW
Utility capacity
Lead participant
Fermi Inc.
Developer
Last updated
Aug 25, 2026
Most recent public record update

About Project Matador HyperGrid Power Site

Project Matador's HyperGrid is an actively financed and permitted private-power development with gas assets, grid supply and longer-term nuclear, solar and battery plans. Project Matador HyperGrid Power Site is located in Texas Panhandle near Amarillo, TX, US and is a generation site in construction status. Participants include Fermi Inc. as developer, Southwestern Public Service Company as utility, Hyundai Engineering & Construction as contractor. Published specifications include 11 GW of stated capacity, 17 GW of stated capacity, 6 GW of onsite generation nameplate. Development comprises SPS grid-supplied bridge power (preconstruction), Initial secured gas-generation assets (construction), Permitted gas buildout (permitted). Key milestones include Incremental TCEQ application filed (2026-03-27) and First three Siemens turbines arrived (2026-07-21). grid supply — 200 MW: 86 MW expected and additional 114 MW targeted but not fully committed. natural gas generation — 2 GW: Approximately 2 GW secured/contracted assets; 780 MW of F-class turbines reached Houston. Permitting includes Clean Air Permit for Project Matador gas generation (approved) and Clean Air Permit application for Incremental gas generation (filed). Capital records include equipment financing facility of 500 USD million for Up-to commitment for three Siemens F-class turbines and related equipment; not full project financing. and high-voltage equipment facility of 200 USD million for Facility arranged by Cape; more than USD 100 million initially committed by Keystone.

Projects sharing a market, utility, or organization.

1 related

Capacity

Utility capacity
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

5 phases · 3 milestones
SPS grid-supplied bridge powerAnnounced Or Preconstruction

Utility supply is distinct from onsite generation.

Initial secured gas-generation assetsUnder Construction

Approximately 2 GW secured/contracted assets; no operating capacity.

Permitted gas buildoutAnnounced Or Preconstruction

Air permit is not construction completion.

Incremental gas buildoutAnnounced Or Preconstruction

Would bring total gas authorization to about 11 GW if approved.

Four-reactor nuclear programAnnounced Or Preconstruction

Long-term 4.4 GW plan; no operating unit.

4 buildings

Feb 25, 2026
TCEQ final air-permit approval
Completed
Mar 27, 2026
Incremental TCEQ application filed
Completed
Jul 21, 2026
First three Siemens turbines arrived
Completed

Infrastructure

Electric GridSecured Or Contracted

200 MW

86 MW expected and additional 114 MW targeted but not fully committed.

Onsite Natural Gas GenerationUnder Construction

2 GW

Approximately 2 GW secured/contracted assets; 780 MW of F-class turbines reached Houston.

Onsite GenerationPermitted Or Installed

6 GW

Air authorization, not installed or operating capacity.

Onsite GenerationPotential Or Planned

4.4 GW

Four-reactor long-term plan; licensing and financing incomplete.

SolarPlanned Or Represented

No site-specific installed MW disclosed.

Battery StoragePlanned Or Represented

No site-specific installed MWh disclosed.

Project map

0 of 1 project point mapped
Infrastructure facts
6
Mapped records
1
Capacity figures
4

No map point available

Power & interconnection: 2Generation & storage: 4

Facts & sources

Published claims and their source links.

17 facts
Base Private Power Plan
11 GW
Actual
Conditional Expanded Power Plan
17 GW
Actual
Gas Generation Air Permit Approved
6 GW
Actual
Incremental Gas Permit Application
5 GW
Actual
Secured Generation Assets Approximately
2 GW
Actual
Sps Grid Service Committed
86 MW
Actual
First Three F Class Turbines Combined Rating Up To
780 MW
Actual
First Three F Class Turbines At Port Of Houston
True
Actual
Site Work To Receive Turbines Underway
True
Actual
First Power Target
2026
Actual
Planned Nuclear Capacity
4.4 GW
Actual
Planned Nuclear Reactors
4 reactors
Actual
First Nuclear Unit Target
2032
Actual
Solar Component Planned
True
Actual
Battery Storage Component Planned
True
Actual
Mu Fg Equipment Facility Up To
$500 million
Actual
Keystone Cape Facility Up To
$200 million
Actual