Cartis diligence evidence schedule
Project Matador HyperGrid Power Site
PRJ-0396 · Site · Texas Panhandle near Amarillo, Texas, United States
Captured 2026-09-06T04:12:51.871Z · Record last updated 2026-08-25
SHA-256: 8d2b5bb4a2b34a811d6dc47fb51f13821a971344d6f42a39f09d089fd5ffa2cb
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
Project Matador's HyperGrid is an actively financed and permitted private-power development with gas assets, grid supply and longer-term nuclear, solar and battery plans. Project Matador HyperGrid Power Site is located in Texas Panhandle near Amarillo, TX, US and is a generation site in construction status.
Headline: 86 MW Utility capacity
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Base Private Power Plan · 11 GW
actual · Project Matador HyperGrid Power Site (project)
Claim 36688 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm - Fermi 2025 Form 10-K
U.S. Securities and Exchange Commission · Document date: 2026-03-30 · Corroborating
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000010/frmi-20251231.htm
Conditional Expanded Power Plan · 17 GW
actual · Project Matador HyperGrid Power Site (project)
Claim 36689 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm - Fermi files additional 5 GW clean-air permit and describes 17 GW plan
Fermi America · Document date: 2026-03-14 · Corroborating
https://fermiamerica.com/worlds-largest-private-grid-fermi-america-to-file-additional-5gw-clean-air-permit-for-project-matador-with-the-texas-commission-on-environmental-quality-tceq-upsizing-campus-proje/ - Project Matador current project website
Fermi America · Document date: Not published · Corroborating
https://fermiamerica.com/
Gas Generation Air Permit Approved · 6 GW
actual · Project Matador HyperGrid Power Site (project)
Claim 36690 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm - Fermi receives final clean-air permit approval
Fermi America · Document date: 2026-02-25 · Corroborating
https://fermiamerica.com/fermi-america-receives-nations-second-largest-clean-air-permit-for-project-matador/
Incremental Gas Permit Application · 5 GW
actual · Project Matador HyperGrid Power Site (project)
Claim 36691 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm - Fermi 2025 Form 10-K
U.S. Securities and Exchange Commission · Document date: 2026-03-30 · Corroborating
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000010/frmi-20251231.htm
Secured Generation Assets Approximately · 2 GW
actual · Project Matador HyperGrid Power Site (project)
Claim 36692 · Review: Approved · Claim date: Not published
- Fermi Q1 2026 earnings release
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000027/fermi1q26erex_991.htm - Project Matador current project website
Fermi America · Document date: Not published · Corroborating
https://fermiamerica.com/
Sps Grid Service Committed · 86 MW
actual · Project Matador HyperGrid Power Site (project)
Claim 36693 · Review: Approved · Claim date: Not published
- Fermi 2025 Form 10-K
U.S. Securities and Exchange Commission · Document date: 2026-03-30 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000010/frmi-20251231.htm
First Three F Class Turbines Combined Rating Up To · 780 MW
actual · Project Matador HyperGrid Power Site (project)
Claim 36695 · Review: Approved · Claim date: Not published
- First Siemens Energy turbines arrive for Project Matador
Fermi America · Document date: 2026-07-21 · Primary
https://fermiamerica.com/first-siemens-turbines-arrive-for-project-matador/
First Three F Class Turbines At Port Of Houston · True
actual · Project Matador HyperGrid Power Site (project)
Claim 36696 · Review: Approved · Claim date: Not published
- First Siemens Energy turbines arrive for Project Matador
Fermi America · Document date: 2026-07-21 · Primary
https://fermiamerica.com/first-siemens-turbines-arrive-for-project-matador/
Site Work To Receive Turbines Underway · True
actual · Project Matador HyperGrid Power Site (project)
Claim 36697 · Review: Approved · Claim date: Not published
- First Siemens Energy turbines arrive for Project Matador
Fermi America · Document date: 2026-07-21 · Primary
https://fermiamerica.com/first-siemens-turbines-arrive-for-project-matador/
First Power Target · 2026
Planned / design or future potential · Project Matador HyperGrid Power Site (project)
Claim 36699 · Review: Approved · Claim date: Not published
- Project Matador current project website
Fermi America · Document date: Not published · Primary
https://fermiamerica.com/
Planned Nuclear Capacity · 4.4 GW
Planned / design or future potential · Project Matador HyperGrid Power Site (project)
Claim 36701 · Review: Approved · Claim date: Not published
- Fermi files additional 5 GW clean-air permit and describes 17 GW plan
Fermi America · Document date: 2026-03-14 · Primary
https://fermiamerica.com/worlds-largest-private-grid-fermi-america-to-file-additional-5gw-clean-air-permit-for-project-matador-with-the-texas-commission-on-environmental-quality-tceq-upsizing-campus-proje/
Planned Nuclear Reactors · 4 reactors
Planned / design or future potential · Project Matador HyperGrid Power Site (project)
Claim 36702 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm
First Nuclear Unit Target · 2032
Planned / design or future potential · Project Matador HyperGrid Power Site (project)
Claim 36703 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm
Solar Component Planned · True
Planned / design or future potential · Project Matador HyperGrid Power Site (project)
Claim 36704 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm - Project Matador current project website
Fermi America · Document date: Not published · Corroborating
https://fermiamerica.com/
Battery Storage Component Planned · True
Planned / design or future potential · Project Matador HyperGrid Power Site (project)
Claim 36705 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm - Project Matador current project website
Fermi America · Document date: Not published · Corroborating
https://fermiamerica.com/
Mu Fg Equipment Facility Up To · $500 million
actual · Project Matador HyperGrid Power Site (project)
Claim 36706 · Review: Approved · Claim date: Not published
- Fermi Form 10-Q for quarter ended March 31, 2026
U.S. Securities and Exchange Commission · Document date: 2026-05-14 · Corroborating
https://www.sec.gov/Archives/edgar/data/2071778/000207177826000032/frmi-20260331.htm - Fermi MUFG equipment financing 8-K
U.S. Securities and Exchange Commission · Document date: 2026-02-10 · Primary
https://www.sec.gov/Archives/edgar/data/2071778/000121390026014270/ea0276274-8k_fermi.htm
Keystone Cape Facility Up To · $200 million
actual · Project Matador HyperGrid Power Site (project)
Claim 36707 · Review: Approved · Claim date: Not published
- Fermi Keystone/Cape equipment facility
Fermi America · Document date: 2026-02-19 · Primary
https://fermiamerica.com/fermi-america-makes-initial-draw-on-200-million-equipment-facility-from-keystone-national-group-and-cape-commercial-finance-to-accelerate-the-delivery-of-the-first-2-3gw-of-project-matador/
Counterparties and capital
Fermi Inc. · Developer · CMP-0981
Hyundai Engineering & Construction · Contractor · CMP-0987
Siemens Energy · Supplier · CMP-0197
Southwestern Public Service Company · Utility Provider · CMP-0983
$500,000,000 · 2026-02-10
Up-to commitment for three Siemens F-class turbines and related equipment; not full project financing.
Fermi Inc. (Sponsor And Indirect Borrower) · MUFG (Lender)
Financing record 117; claim-specific source links appear in the exhibit sources where published.
$200,000,000 · 2026-02-19
Facility arranged by Cape; more than USD 100 million initially committed by Keystone.
Cape Commercial Finance (Arranger) · Fermi Inc. (Sponsor) · Keystone National Group (Lender)
Financing record 118; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.