Project Matador Data Center Campus

Texas Panhandle near Amarillo, Texas, United StatesPreconstruction
Capacity
No public figure
Lead participant
Fermi Inc.
Developer
Last updated
Aug 25, 2026
Most recent public record update

About Project Matador Data Center Campus

Project Matador's data center component is a tenant-gated powered-shell campus on Texas Tech-controlled land. Project Matador Data Center Campus is located in Texas Panhandle near Amarillo, TX, US and is a data center campus in preconstruction status. Participants include Fermi Inc. as developer, Texas Tech University System as landowner. Published specifications include 200 MW of stated capacity. Development comprises Preliminary site development (construction), First powered-shell campus (preconstruction). Key milestones include Qualifying tenant lease and TTU notice condition (2026-12-31) and First powered shell target (2027-12-31). water supply: Groundwater leases disclosed; sustainable yield and tenant allocation remain open. fiber backhaul: High-capacity fiber described; carrier and lit-service evidence remain open. Incentives include property tax abatement (approved) for Project Matador reinvestment zone and 10-year abatement; rate and eligible property basis not disclosed in filing summary.

Projects sharing a market, utility, or organization.

1 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

2 phases · 4 milestones
Preliminary site developmentUnder Construction

Does not constitute vertical powered-shell construction.

First powered-shell campusAnnounced Or Preconstruction

At least 200 MW tenant condition disclosed.

Jan 1, 2025
Preliminary site development began
Completed
Dec 11, 2025
Prospective tenant terminated unfunded AIAC
Completed
Dec 31, 2026
Qualifying tenant lease and TTU notice condition
Forecast
Dec 31, 2027
First powered shell target
Forecast

Infrastructure

Water SupplyUnder Construction

Groundwater leases disclosed; sustainable yield and tenant allocation remain open.

FiberPlanned Or Represented

High-capacity fiber described; carrier and lit-service evidence remain open.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Cooling & water: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

8 facts
Leased Site Area
5,236 acres
Actual
Expanded Site Area Expected
7,570 acres
Actual
Planned Compute Space
15 million square feet
Actual
Preliminary Site Development Started
2025
Actual
Vertical Construction Requires Definitive Tenant Lease
True
Actual
Ttus Notice To Proceed Required
True
Actual
First Powered Shell Operations Target
2027
Actual
Phase Zero One Incremental Capex Over
$3 billion
Actual