PowerHouse 95 Spotsylvania Campus

Route 17 / Turner Road area, Virginia, United StatesUnder construction
Evidence
Planned / design
300 MW
Updated
Oct 28, 2026

PowerHouse 95 is an active Spotsylvania data center campus whose current operator plan reaches 900 MW of maximum utility power across up to 12 buildings. The figure is a campus utility envelope, planned utility capacity.

Capacity

Current maximum utility power

Reported rounded

900 MW

Source

Phase ii additional capacity purpose

Planned / design or future potential

300 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Phase I / PH95 NorthUnder construction

2 buildings

County public page describes two two-story buildings totaling 512,564 sf; local permits identify subpackages.

Phase IIUnder construction

3 buildings

USACE notice covers three buildings plus substation/transmission; federal authorization remains pending.

Milestones (6)
Historical 800 MW campus plan announced

Feb 22, 2024 · Recorded actual event

Completed · Announced

Source not linked
PH95 North construction announced

Jun 13, 2024 · Recorded actual event

Completed · Construction started

Source not linked
Phase 1B clearing/grading permit issued

Oct 16, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked
Phase II wetland public notice opened

Jan 28, 2026 · Recorded actual event

Completed · Permit filed

Source not linked
County report records Phase 2A clearing/grading issuance

Mar 3, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
Operator's current first-delivery target

Q3 2026 · Forecast / planned record

Forecast · Event type not stated

Source not linked

Participants

Harrison Street

Investor

Sources by role
Investor (1)
PowerHouse Data Centers

Operator

Sources by role
Operator (1)
Operator (1)

Site & development

Maximum building height

Source report

2 stories

Source

Current construction window start

Source report

2024-Q2

Source

Current construction window end

Source report

2027-Q4

Source

Phase i site area

Source report

110 acres

Source

Phase i building count

Source report

2 buildings

Source

Phase i floor area

Source report

512,564 square feet

Source

Phase i building height

Source report

2 stories

Source

Phase ii building count

Source report

3 buildings

Source

Phase ii pem wetland impact

Source report

1.49 acres

Source

Phase ii pfo wetland impact

Source report

0.84 acres

Source

Phase ii wetland mitigation credits

Source report

3.17 credits

Source

Additional project facts

Physical campus count

Source report

1 campus

Source

Current delivery target

Source report

2026-Q3

Source

Phase ii federal permit status

Source report

Public notice / under evaluation

Source

Phase ii intermittent stream impact

Source report

693 linear feet

Source

Phase ii stream mitigation credits

Source report

1,026 credits

Source

Three substation concept

Source report

3 substations

Source

Operating capacity disclosed

Source report

False

Source

Current utility envelope is IT capacity

Source report

False

Source

Federal public notice is permit approval

Source report

False

Source

Phase i and phase ii aggregate as separate campuses

Source report

False

Source

Infrastructure & permits

Technical details (3)
Electric grid

Planned or represented

900 MW maximum utility

Current campus marketing envelope; not operating IT capacity.

Electric grid

Reported context

3 substations

Historical plan described three 300 MW substations; energization and current sizing are not publicly disclosed.

Electric grid

Planned or represented

300 MW additional-capacity purpose

USACE purpose statement; federal authorization remains pending.

Project map

Project map

1 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
3
Power & interconnection: 3
Permit · Status not stated

Phase 1B

Spotsylvania County

Oct 16, 2025

Sources (2)
Permit · Status not stated

Building B

Spotsylvania County

Oct 24, 2025

Sources (1)
Permit · Status not stated

Building A

Spotsylvania County

Oct 31, 2025

Sources (1)
Permit · Status not stated

Phase II

U.S. Army Corps of Engineers Norfolk District

Jan 28, 2026

Sources (1)
Permit · Status not stated

Phase 2A

Spotsylvania County

Mar 3, 2026

Sources (2)

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (3)
PowerHouse Arcola Building 1

Under construction · Arcola / Sterling, Virginia, United States

Shared participant: PowerHouse Data Centers · Same market: Virginia, United States

Compare in a collection
PowerHouse Arcola Building 2

Under construction · Arcola / Sterling, Virginia, United States

Shared participant: PowerHouse Data Centers · Same market: Virginia, United States

Compare in a collection
PowerHouse Arcola Campus

Under construction · Arcola / Sterling, Virginia, United States

Shared participant: PowerHouse Data Centers · Same market: Virginia, United States

Compare in a collection