PowerHouse Arcola Campus

Arcola / Sterling, Virginia, United StatesUnder construction
Capacity
120 MW
Utility capacity
Lead participant
American Real Estate Partners
Developer
Last updated
Aug 25, 2026
Most recent public record update

About PowerHouse Arcola Campus

PowerHouse Arcola Campus encompasses shared land, utilities, lease and two buildings; 120 MW is maximum utility capacity, planned utility capacity.

Program relationships

0 linked

Projects sharing a market, utility, or organization.

1 related

Capacity

Utility capacity
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Utility Service120 MWReported Rounded · PowerHouse Arcola Campus

Development

1 phases · 5 milestones
Shared campus construction and utility deliveryUnder Construction

Current sponsor property page forecasts July 2027 delivery; another sponsor page says Q1 2027 and power Q3 2027.

2 buildings

Sep 13, 2022
Arcola launch design announced
Completed
Apr 1, 2024
Campus construction began
Completed
Jan 15, 2026
Long-term hyperscale lease announced
Completed
Jul 1, 2027
Current AREP campus delivery forecast
Forecast
Jul 1, 2027
PowerHouse power-delivery forecast
Forecast

Infrastructure

Electric GridUnder Construction

120 MW maximum utility

Campus maximum utility capacity with on-site substations; executed service agreement and energization evidence not public.

FiberPlanned Or Represented

Proximity and routes to Northern Virginia fiber hubs including Ashburn and Manassas.

Cooling SystemPlanned Or Represented

High-density and liquid-cooling readiness; deployed customer configuration undisclosed.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Cooling & water: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

17 facts
Physical Building Count
2
Fact
Building Story Count
2 stories per building
Fact
Current Developable Area
615,000 square feet
Fact
Current Site Area
30 acres
Fact
Lease Announcement Site Area
37 acres
Fact
Maximum Utility Capacity
120 MW
Reported Rounded
Construction Started
2024-04
Actual
Forecast Delivery
2027-07
Actual

Sources report a conflicting figure.

Forecast Construction Delivery
2027-Q1
Actual

Sources report a conflicting figure.

Forecast Power Delivery
2027-Q3
Actual
Lease Status
Long term hyperscale lease executed
Actual
Tenant Identity
Undisclosed
Actual
Lease Capacity Coverage
Not disclosed
Actual
Onsite Substation Design
True
Fact
Liquid Cooling Ready
True
Fact
Target Certification
LEED BD+C
Actual
Fiber Market Access
Ashburn and Manassas
Actual