Meta Sturgeon County Data Centre
- Planned critical IT
- 1,000 MW
- Updated
- Oct 28, 2026
- Utility
- AESO grid allocation; Capital Power energy agreement; later Greenlight generation
Meta announced groundbreaking for its initial 1 GW Sturgeon County campus in July 2026; its builder reports preparation and mobilization underway. This is planned compute capacity, not operating IT. Counsel describes approximately 1.8 GW at full build. Initial grid service and a 250 MW Capital Power agreement precede the separate 932 MW first Greenlight phase targeted for H2 2030. Initial load service is forecast for H2 2028, while the province lists construction through 2029. Meta plans closed-loop liquid and dry cooling without operational cooling-water use, but domestic, fire and maintenance water remain. October's piling-only notice is not effective until November 10. Site financing terms, fee title and the final permit-appeal outcome remain unverified.
Capacity
Potential full build scale — not additive to initial campus
Planned / design or future potentialApproximately 1.8 GW at full build; optional expansion, not operating capacity
SourceSeparate Greenlight phase 1 generation capacity
Planned separate generation nameplate; not IT load932 MW
Generation capacity; not IT capacity
SourcePlanned campus cooling system
Planned / design or future potentialClosed loop liquid and dry cooling; no operational cooling water use, not zero total site water
SourceUtility service agreement
Capital Power capacity and energy agreement over ten years; not operating IT250 MW
SourceSeparate Greenlight permitted two stage generation
Permitted generation nameplate; first 932 MW is a subset, not additive1,864 MW
Generation capacity; not IT capacity
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Participants
Campus developer and intended operator
Separate generation developer
Grid system operator
Other participants (6)
General contractor
Utility energy agreement counterparty
Transmission planning partner
Separate generation partner
Construction management partner
Meta transaction legal counsel
Capital & incentives
Capital claims
Campus investment estimate — not a financing close
Project cost estimate not financingCAD 13,000,000,000+
SourcePlanned local infrastructure commitment
Project cost estimate not financingApproximately CAD 60,000,000
SourceSeparate Greenlight ownership and financing scope
Platform level transactionGreenlight plant financing and equity interests belong to the power asset, not the Meta campus; no allocation to campus financing
SourceSite & development
Historical county construction start forecast
Historical forecast; July groundbreaking and preparation subsequently announced2026-H2
SourceHistorical utility allocation disclosure
Historical differing allocation, not additive907 MW in Pembina October 2025 disclosure; current AESO page gives 970 MW, change basis not explained
SourceCampus site area
Province description, not cadastral fee title verificationApproximately 1,750 acres
SourceProvincial construction schedule
Government schedule forecast2026–2029; Not an achieved opening or all at once IT delivery
SourceTechnical specifications
Annual clean and renewable energy matching commitment
Company commitment; not physical 24/7 renewable supply100 percent
SourceCampus water use scope
Design and service descriptionMunicipal potable service described; no operational cooling water use planned, but domestic, fire and maintenance uses remain. Actual total consumption not established
SourceAdditional project facts
Separate Greenlight phase 1 target operation
Company forecast, not achieved generation or campus opening2030-H2
SourceInitial load service forecast
Company forecastH2 2028 for 250 MW agreement; not commissioning of the entire campus
SourceCurrent builder reported site stage
Current contractor statementPlanning, procurement, mobilization and site preparation underway; not completed main buildings
SourceGovernment public support statement
Attributed government policy statementAlberta states no public subsidies, grants or discounted power; county policy gives no municipal incentives. Exhaustive tax/support position not independently established
SourceDP-26-0028 56111 Range Road 223 regulatory record
Master site developmentApproval notice issued. Notice states July 7 effective date. Not all building permits. Final appeal disposition not established.
SourceDP-26-0293 DCB01 / MY01 56027 Range Road 223 regulatory record
Piling onlyIssued not yet effective. November 10 stated effective date is future at cutoff. Not full building approval or achieved piling.
SourceAUC 30261-D02-2026 separate Greenlight plant regulatory record
Power plant approval reasonsReasons issued. References June 19 initial approval. 1,864 MW two stage plant; not campus permit. Water agreement conditions remain separate.
SourceInfrastructure & permits
Technical details (7)
Planned separate generation nameplate; not IT load
932 MW
Company design commitment
Closed-loop liquid and dry cooling; no operational cooling-water use, not zero total site water
Executed load allocation, not energized IT
970 MW
Historical differing allocation, not additive
907 MW in Pembina October 2025 disclosure; current AESO page gives 970 MW, change basis not explained
Capital Power capacity and energy agreement over ten years; not operating IT
250 MW
Permitted generation nameplate; first 932 MW is a subset, not additive
1,864 MW
Design and service description
Municipal potable service described; no operational cooling-water use planned, but domestic, fire and maintenance uses remain. Actual total consumption not established
Project map
Separate Greenlight permitted two stage generation · Permitted generation nameplate; first 932 MW is a subset, not additive
Meta Sturgeon County Data Centre
Jun 25, 2026
DP-26-0028 56111 Range Road 223 regulatory record · Approval notice issued. Notice states July 7 effective date. Not all building permits. Final appeal disposition not established.
Meta Sturgeon County Data Centre
Jun 16, 2026
DP-26-0293 DCB01 / MY01 56027 Range Road 223 regulatory record · Issued not yet effective. November 10 stated effective date is future at cutoff. Not full building approval or achieved piling.
Meta Sturgeon County Data Centre
Oct 20, 2026
AUC 30261-D02-2026 separate Greenlight plant regulatory record · Reasons issued. References June 19 initial approval. 1,864 MW two stage plant; not campus permit. Water agreement conditions remain separate.
Meta Sturgeon County Data Centre
Jun 25, 2026
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (3)
Preconstruction · Sturgeon County, Alberta, Canada
Same locality: Sturgeon County
Compare in a collectionProposed · near High River, Alberta, Canada
Shared participant: Alberta Electric System Operator · Same market: Alberta, Canada
Compare in a collectionProposed · Olds, Alberta, Canada
Shared participant: Alberta Electric System Operator · Same market: Alberta, Canada
Compare in a collection